Administrative Rules of Montana
Department 38 - PUBLIC SERVICE REGULATION
Chapter 38.5 - UTILITY DIVISION
Subchapter 38.5.20 - Least Cost Planning - Electric Utilities
Rule 38.5.2021 - DEFINITIONS
Current through Register Vol. 18, September 20, 2024
(1) "Action plan period" means the five-year period beginning with the calendar year after the filing of a resource plan.
(2) "Adequate" means, with respect to an electric system owned or controlled by a utility, the ability to supply the aggregate electrical demand and energy requirements of the utility's customers at all times, taking into account scheduled and reasonably expected unscheduled outages of system elements.
(3) "Affiliate" means, for purposes of this rule, a parent, subsidiary, division, or the like, regardless of designation, owning or controlling the utility, owned or controlled by the utility, under common ownership with the utility, or under common control with the utility.
(4) "Assessment" means a documented process used by a utility to make informed judgments regarding elements of a resource plan and action plan based on the careful consideration of quantitative and qualitative information and the input of stakeholders, the public, and the advisory committee required in 69-3-1208, MCA.
(5) "Cost" means the actual or forecast costs incurred to own, operate, and manage existing and potential new resources sufficient to provide adequate and reliable services over the planning period including, but not limited to, costs for:
(6) "Cost-effective" means that a project or resource is forecast:
(7) "Environmentally responsible" means explicitly recognizing and incorporating into resource plans, resource planning processes, and resource procurement the policy of the State of Montana to encourage utilities to acquire resources in a manner that will help ensure a clean, healthful, safe, and economically productive environment.
(8) "Externalities" has the meaning in 69-3-1203(6), MCA.
(9) "Long-term" means a time period at least as long as the planning period.
(10) "Planning period" has the meaning in 69-3-1203(9), MCA.
(11) "Reliable" means a power system that is adequate and can withstand sudden disturbances, such as electrical short circuits or unanticipated loss of system elements.
(12) "Resources" includes all of the following:
(13) "Service" means required and optional electricity and/or electricity-related products or services provided by a utility to retail customers including metering, billing, distribution, transmission, generation, and generation-related services. Services include, but are not limited to, traditional electricity supply and delivery service, renewable energy-sourced offerings, interconnection and integration of distribution side and customer generators, net metering, demand and/or bill management programs, information-based services such as energy audits, transmission ancillary services, street lighting services, and other services for which a utility has filed or would be required to file a tariff.
(14) "Societal cost" means all costs to a utility plus externalities.
(15) "Stakeholder" means a member of the public (individual, corporation, organization, group, etc.) who may have an interest in, or may be affected by, these rules.
AUTH: 69-3-1204, 69-3-1206, MCA; IMP: 69-3-1204, 69-3-1205, 69-3-1206, 69-3-1207, 69-3-1209, MCA