Administrative Rules of Montana
Department 38 - PUBLIC SERVICE REGULATION
Chapter 38.5 - UTILITY DIVISION
Subchapter 38.5.19 - Cogeneration and Small Power Production
Rule 38.5.1905 - RATES FOR PURCHASES
Current through Register Vol. 18, September 20, 2024
(1) Each utility shall purchase available power from any qualifying facility at:
(2) The rate paid by the utility for any purchase shall not exceed the utility's avoided costs. Avoided costs will be calculated as provided in this rule, unless the utility and the qualifying facility agree upon a different rate.
(3) When required by FERC regulation and to the extent practicable, the Commission's determination of avoided costs will take into account the factors described in 18 CFR 292.304(e).
(4) If a qualifying facility has provided in its contract with a utility that measurement of facility energy input to the utility system and measurement of facility load will be accomplished with one meter, the utility shall pay the purchase rate only for the facility's input to the system which is in excess of the facility's load.
(5) If the qualifying facility has agreed in its contract with a utility that measurement of facility input to the utility system shall be accomplished by metering separate from that measuring the facility load, the qualifying facility may receive payment for all of the energy it supplies to the utility according to the applicable schedule of standard rates for purchases. Unless the qualifying facility has contracted for a different rate, the standard rate is applicable regardless of whether the qualifying facility is simultaneously served by the utility for the facility's load, and regardless of the rate charged by the utility for such simultaneous sales.
AUTH: 69-3-103, MCA; IMP: 69-3-102, MCA