(1) The breach of an earth dam must be excavated down to the level of the natural ground and be able to pass the 100-year, 24-hour flood at a depth and velocity equivalent to the natural channel. However, the maximum width required may be the total removal of the dam.

(2) The sides of the breach must be excavated to a slope that is stable and consistent with the natural angle of repose of adjacent material abutting the dam or as determined by the engineer.

85-15-110, MCA; IMP, 85-15-210, 85-15-213, MCA;

Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.