Administrative Rules of Montana
Department 36 - NATURAL RESOURCES AND CONSERVATION
Chapter 36.14 - DAM SAFETY
Subchapter 36.14.4 - Operation Application and Permit
Rule 36.14.402 - OPERATION PERMIT APPLICATION - GENERAL REQUIREMENTS
Current through Register Vol. 18, September 20, 2024
(1) Applications, including applications for renewal of a permit to operate high-hazard dams must include:
(2) The requirements in (1)(b) through (d) do not apply for a new dam for which a construction permit has been issued. The report of the evaluation must be of the dam in its condition and configuration at the time of the application and must be submitted within 90 days of the visual inspection. If the owner of the dam has opted to split the visual inspection into two separate visits to the dam site, the 90-day requirement begins with the date of the second visual inspection.
(3) Within 30 days of receipt of a permit application, the department shall:
(4) After receipt of all required information, the department shall issue or deny the permit within 90 days, but not before approval of any construction pursuant to a construction permit.
AUTH: 85-15-110, 85-15-213, MCA; IMP: 85-15-212, MCA