(1) Boiler repairs shall be made in accordance with established standards, procedures and the ASME code(s) adopted and incorporated in ARM 24.301.710.

(2) The department, at its discretion, may require documentation which verifies repairs were completed in compliance with established standards, procedures and the ASME code(s). Documentation may include welding certifications, weld records, certification by a design professional, national board "R" symbol stamp or other verifiable documentation acceptable to the department.

(3) Weld repairs to boilers shall not be initiated without authorization of the department or special boiler inspector if the boiler is insured by an authorized insurance company. Other repairs to boilers shall be reported to the department, by the party performing the work, within 30 days of completion of the work.

(4) Failure to report boiler repairs to the department, within 30 days of completion of the work, or to provide documentation as required in (2) above, may cause the department to deny issuance of the boiler operating certificate until such time as the imposed requirements are met.

50-60-203, 50-74-101, MCA; IMP, 50-60-203, 50-74-102, 50-74-207, 50-74-215, 50-74-218, MCA;

Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.