Administrative Rules of Montana
Department 24 - LABOR AND INDUSTRY
Chapter 24.301 - BUILDING CODES
Subchapter 24.301.5 - Requirements for Recreational Vehicles and Factory-Built Buildings
Rule 24.301.543 - IN-PLANT QUALITY CONTROL
Current through Register Vol. 6, March 22, 2024
(1) The manufacturer shall submit a manual or shall reference an applicable manual previously reviewed by the bureau, outlining a program of quality control concurrent with their request for plan review. The program outlined must meet the standards of and be reviewed and approved by the bureau. In addition, the manufacturer shall designate a company or corporate officer or other responsible person to be responsible for the quality control program, and shall maintain records to substantiate that each unit has been inspected and complies with the plans as reviewed and approved by the bureau. The bureau may make periodic inspections and may condition the issuance of insignia on compliance with these rules by the manufacturer. Approval of in-plant quality control does not constitute approval of any submitted application, plans, or insignia.
(2) The following specific information is required for the quality control manual:
AUTH: 50-60-203, 50-60-401, MCA; IMP: 50-60-203, 50-60-401, MCA