Current through Register Vol. 18, September 20, 2024
(1) Electrical power and lighting installations for amusement or public assembly may be permitted for a period not to exceed 30 days. The installation must comply with Article 525 of the National Electrical Code.
(2) The electrical inspection fee for each temporary installation shall be $45 for the entirety of the temporary installation, provided that such inspection can be completed within one hour. If additional inspection time is required, it will be charged at the rate of $25 for each additional 30 minutes or fractional parts thereof.
(3) Each time a temporary amusement or public assembly electrical installation is erected or relocated, another electrical inspection will be required.
AUTH: 50-60-203, 50-60-603, MCA; IMP: 50-60-201, 50-60-203, 50-60-603, 50-60-604, MCA