(1) Public contracting agencies shall not divide a public works project into more than one contract for the purpose of avoiding compliance.
(2) When making a determination of whether the public agency divided a contract to avoid compliance, the commissioner shall consider the facts and circumstances in any given situation including, but not limited to, the following matters:
(3) When the commissioner determines that a public contracting agency has divided a public works project to avoid compliance, the commissioner shall issue an order compelling compliance. The order shall be written and shall offer the public contracting agency the opportunity to contest the order.
18-2-431, MCA; IMP, 18-2-401, 18-2-402, 18-2-403, MCA;