(1) A public contracting agency must include in the bid specifications and contracts for any public works the following:
(2) If a contract for public works is to be performed in more than one district where a different standard prevailing rate of wages is established for a particular craft, classification or type of worker, the highest rate is the rate to be included in the bid specifications and contract provision.
(3) Whenever a public works project is accepted by a public contracting agency, the agency shall promptly send to the department a notice of acceptance and the completion date of the project. This notice is required only if the public works project is covered by the Act.
(4) If a public contracting agency fails to comply with the requirements of this rule, the obligation to pay the standard prevailing rate of wages will be placed on the public contracting agency and the contractor may be relieved of such obligation.
18-2-409, 18-2-431, MCA; IMP, 18-2-401, 18-2-403, 18-2-421, 18-2-422, MCA;