(1) If an owner fails to decommission a facility in either the manner or schedule set forth in the decommissioning plan under ARM 17.86.105 and did not commence action to rectify deficiencies within 90 days after the department's notification was mailed, the department may cause the bond to be forfeited for the entire facility. The department shall notify the owner and the surety by certified mail.

(2) The notification in (1):

(a) must include the reasons for forfeiture and the amount to be forfeited; and

(b) is a final decision of the department.

AUTH: 75-26-310, MCA; IMP: 75-26-309, MCA

Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.