(1) Except as provided in (3) through (5), an owner shall submit a bond payable to the state of Montana in a form acceptable to the department under ARM 17.86.115 and in a sum determined by the department under ARM 17.86.106, conditioned on the faithful decommissioning of the facility. The owner shall submit the bond by the applicable deadline in (2).
(2) Except as provided in (3) through (5):
(3) If a facility is repurposed, as determined by the department in consultation with the owner, the owner is not required to provide a bond and any existing bond must be released until the repurposed facility reaches its fifth year of operation. The owner shall submit all revised information required in ARM 17.86.102(2)(b) within six months after a facility is repurposed. Within five years after a facility is repurposed, the owner shall submit to the department a bond payable to the state of Montana in a form acceptable by the department under ARM 17.86.115 and in a sum determined by the department under ARM 17.86.106, conditioned on the faithful decommissioning of the facility.
(4) An owner is exempt from submitting a bond when a private landowner on whose land the entire facility is located owns a 10 percent or greater share of the facility, as determined by the department.
(5) An owner is exempt from submitting a bond for the facility or portion of the facility for which the owner: