(1) For an emergency renovation operation, as defined in 40 CFR 61.141, the owner or operator of the facility shall:

(a) no later than the following working day, notify the department by submitting a completed emergency notification form and the fee specified in ARM 17.74.406, ensuring the submittal contains all the information required to establish that the conditions for an emergency renovation operation, as defined in 40 CFR 61.141, are met; and

(b) within five working days of submitting the notification in (a), submit to the department a full asbestos project permit application pursuant to ARM 17.74.355 and additional fees under ARM 17.74.406.

(2) For ordered demolitions pursuant to 40 CFR 61.145(a)(3), the owner or operator shall submit a completed ordered demolition notification form and the fee specified in ARM 17.74.406, ensuring the submittal contains all the information required to explain why the conditions under 40 CFR 61.145(a)(3) are met.

(3) Emergency renovation operations under (1) and ordered demolitions under (2) may commence immediately after the notification and the fee for those activities are submitted to the department.

AUTH: 75-2-503, MCA; IMP: 75-2-503, 75-2-511, MCA

Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.