(1) An asbestos contractor/supervisor shall be:
(a) physically
present at all times at the work site when permitted work is being conducted on an
asbestos project;
(b) accessible to all
asbestos workers; and
(c) responsible
for ensuring that the asbestos project complies with the asbestos project permit and
the project design.
(2) Alternate control measures that are equivalent to those required under this subchapter may be used if written approval is obtained from the department in advance pursuant to ARM 17.74.353.
AUTH: 75-2-503, MCA; IMP: 75-2-503, MCA
Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.