Administrative Rules of Montana
Department 17 - ENVIRONMENTAL QUALITY
Chapter 17.24 - RECLAMATION
Subchapter 17.24.6 - Strip and Underground Mine Reclamation Act: Transportation Facilities, Use of Explosives, and Hydrology
Rule 17.24.650 - POSTMINING REHABILITATION OF SEDIMENTATION PONDS, DIVERSIONS, IMPOUNDMENTS, AND TREATMENT FACILITIES

Universal Citation: MT Admin Rules 17.24.650

Current through Register Vol. 6, March 22, 2024

(1) Before abandoning the permit area, the operator shall renovate all permanent sedimentation ponds, diversions, impoundments, and treatment facilities to meet criteria specified in the detailed design plan for the permanent structures and impoundments.

(2) All temporary sedimentation ponds, diversions, impoundments and treatment facilities must be regraded to the approximate original contour and reclaimed prior to abandonment of the permit area.

AUTH: 82-4-205, MCA; IMP: 82-4-231, 82-4-232, MCA

Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.