(1) Each operator shall comply with all applicable state and federal laws in the use of explosives.

(2) Blasts that use more than 5 pounds of explosive or blasting agent must be conducted according to the schedule required by ARM 17.24.623.

(3) All blasting operations must be conducted by experienced, trained, and competent persons who understand the hazards involved. Each person responsible for blasting operations must possess a valid certification. See ARM 17.24.1260 through 17.24.1263.

AUTH: 82-4-205, MCA; IMP: 82-4-231, MCA

Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.