(1) An application for revision to a permit must be submitted for departmental review:
(a) for any proposed change(s) in the
operation as described in the original permit and subsequent revisions thereof;
or
(b) when required under ARM
17.24.414.
(2) The operator may not implement the revision before obtaining the department's approval.
(3) An application for major revision:
(a) must comply with subchapter 3, as
appropriate;
(b) is subject to the
public notice and participation provisions of ARM
17.24.401 through
17.24.405; and
(c) must include submittal of a new or
updated probable hydrologic consequence determination, if determined necessary
by the department for adequate permit review.
(4) If impacts change, the department shall update the cumulative hydrologic impact assessment.
AUTH: 82-4-205, MCA; IMP: 82-4-221, MCA
Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.