Rule 17.20.205 - FINAL FIELD REPORTS

Universal Citation: MT Admin Rules 17.20.205

Current through Register Vol. 18, September 20, 2024

(1) After cessation of geothermal investigation, every person shall submit a final field report to the department in an electronic format acceptable to the department.

(2) Within each final field report shall be included a summary of the previous periodic field reports for the entire investigation.

(3) If the investigation ceases 60 days after the initiation of the investigation the periodic field report and the final field report may be the same.

AUTH: 75-20-1001, MCA; IMP: 75-20-1001, MCA

Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.