(1) An application must include:
(a) either a copy of any and all
interconnection and transmission agreements involving the proposed facility, or the
following information for each such agreement:
(i)
a brief description of the obligations of and the benefits to the facility under the
agreement;
(ii) a list of all parties to
the agreement;
(iii) the time period
during which the agreement is in effect;
(iv) a summary of the terms of the agreement;
and
(v) the financial agreements;
and
(b) a description of all
current and planned negotiations with respect to interconnection of the facility and
transmission of energy. The description must include a list of the parties to any
negotiations and a general discussion of the history and current status of the
negotiations.
75-20-105, MCA; IMP, 75-20-211, MCA;
Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.