Administrative Rules of Montana
Department 17 - ENVIRONMENTAL QUALITY
Chapter 17.20 - MAJOR FACILITY SITING
Subchapter 17.20.15 - Application Requirements Facility Description and Design
Rule 17.20.1503 - ENERGY GENERATION FACILITIES, CONSTRUCTION DESCRIPTION
Current through Register Vol. 18, September 20, 2024
(1) An application for a generation or conversion facility must include a preliminary construction schedule, a description of typical equipment, and a description of the sequential steps involved in carrying out major construction activities, including site preparation and an estimate of the amount of ground disturbance. The schedule must include associated facilities and relocations or development of transportation and other public use facilities necessitated by project construction, and methods of maintaining service during these activities.
(2) An application for a generation facility must contain a description of the following:
AUTH: 75-20-105, MCA; IMP: 75-20-211, 75-20-213, MCA