(1) An application must include a list of any reports, documents, studies, or calculations that indicate that the preliminary design specifications and performance objectives for the major components or process areas of the facility are adequate and can be maintained in the continuous operation of the facility. Design peak operating volume or rate must be described, including the length of time the various levels of peak operation can be sustained.
(2) An application must identify design features that were selected to reduce adverse environmental impacts.
(3) An application must describe any design features that are oversized to accommodate future increases in plant capacity.
(4) The engineering description required by (1) of this rule must include the following major facility components or process areas as applicable: boilers, reactors, generators, condensers, shift conversion facilities, cooling facilities, emission control devices, stacks, and catalyst production and regeneration facilities.
(5) An application must contain a description of associated facilities, including:
(6) An application must contain a map, in an electronic format acceptable to the department, showing the proposed location of all facility structures and nonlinear associated facilities at or associated with the proposed site.
AUTH: 75-20-105, MCA; IMP: 75-20-211, 75-20-213, MCA