Section 7 CSR 10-24.140 - Tradeoffs in Design-Build Contracting
Current through Register Vol. 49, No. 18, September 16, 2024
PURPOSE: This rule describes when and how tradeoffs should be used in awarding a design-build contract and documentation of the tradeoff decisions.
(1) At its discretion, the commission may consider the tradeoff technique when it is desirable to award to other than the lowest priced proposer or other than the highest technically rated proposer.
(2) If the commission uses a tradeoff technique, the following is to be clearly stated in the solicitation:
(3) When tradeoffs are performed, the source selection records must include the following: