PURPOSE: This rule describes the modified design-build selection procedures.

(1) Modified design-build selection procedures, the lowest price technically acceptable source selection process, may be used for any project.

(2) The Request for Proposal (RFP) will clearly state the following:

(A) The identification of evaluation factors and significant subfactors that establish the requirements of acceptability; and

(B) That award will be made on the basis of the lowest evaluated price of proposals meeting or exceeding the acceptability standards for noncost factors.

(3) Tradeoffs will not be permitted, unless the tradeoff is in accordance with 7 CSR 10-24.110. However, the commission may incorporate cost-plus-time (A+B) bidding procedures, lane rental, or other cost-based provisions in such contracts.

(4) Proposals will be evaluated for acceptability but not ranked using the noncost/price factors.

(5) Exchanges may occur in accordance with 7 CSR 10-24.300 through 7 CSR 10-24.330.

*Original authority: 226.020, RSMo 1939; 226.030, RSMo 1939, amended 1965, 2003, 2004; and 227.107, RSMo 2002.

Disclaimer: These regulations may not be the most recent version. Missouri may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.