Current through Register Vol. 49, No. 18, September 16, 2024
PURPOSE: This proposed amendment identifies that only
electronic bids will be received and clarifies that the Construction and
Materials Division is responsible for prequalification
determinations.
(1)
Definitions.
(A) The following definitions
apply to this rule:
1. "Commission" means the
Missouri Highways and Transportation Commission and all its members, jointly
and severally;
2. "Department"
means the Missouri Highways and Transportation Department, which may also be
commonly referred to as the Missouri Department of Transportation. "Department"
includes the chief engineer and all other officers and employees of the
department, unless the text of this rule clearly indicates a contrary
construction is intended;
3. "Chief
engineer" means the chief engineer of the department; or if that position is
vacant, then it means the assistant chief engineer;
4. "Highway project" means any type or
combination of excavation, construction, demolition, maintenance, fabrication,
paving, dredging, repair, erection, electrical, landscaping, seeding and
mulching, erosion control, installation, manufacturing, transportation, or
other work, done under a contract with the commission or department on or for
any existing or proposed road, highway, or bridge in the Missouri state highway
system;
5. "Contract" means a
written agreement between a contractor and the commission or department,
including, but not limited to, a purchase order or similar writing. A contract
may include two (2) or more different highway projects as part of a required or
permissive combination; and
6.
"Cost estimate" means the contractor's own estimate, in the form of a complete
and responsive bid, submitted by a contractor for a highway project.
7. All bids shall be submitted electronically
using the department's electronic bidding process.
(B) For purposes of this rule, work performed
for or under contract with the commission is also performed for the department,
and work performed for or under contract with the department is also performed
for the commission. The term "work" shall be construed liberally in determining
whether work has been performed for the department or commission. Work
performed as a subcontractor on a project for the department or commission
shall be deemed work performed for the department.
(C) For purposes of this rule, bids opened by
the department are deemed to be opened by or for the commission as well, unless
the circumstances clearly require a contrary conclusion.
(2) Application of this Rule.
(A) This rule does not apply to-
1. Any contractor which has a valid
prequalification contractor questionnaire on file with the department, and
which contractor (including, in the case of a partnership or joint venture, any
component contractor) has performed any work for the department within the five
(5) years preceding the date that contractor's bid for any highway project, or
combination of projects, shall be opened by the department;
2. Any contractor which has a valid
prequalification contractor questionnaire on file with the department, which
has performed no work for the department within the five (5) years preceding
the date that contractor's bid for any highway project or combination of
projects shall be opened by the department, and which submits a bid (or cost
estimate) on each individual highway project at or below two (2) million
dollars; and
3. A contractor which
meets the requirements of either paragraph (2)(A)1. or 2. of this rule is
exempt from having to be prequal-ified to bid under section
227.105,
RSMo, effective August 28, 1996.
(B) This rule applies only to a contractor
which intends to or does submit a bid (or cost estimate) in excess of two (2)
million dollars) for any one (1) highway project, whether that highway project
is bid separately or in combination with any other highway project(s); and
further, that contractor must have performed no highway project work for the
department in the five (5) years preceding the date the department shall or
does open that contractor's bid on that highway project.
(3) Contractor Prequalification Required to
Bid, When.
(A) The department shall not accept
any bid (or cost estimate) in excess of two (2) million dollars for a single
highway project (whether it is bid individually or in combination with others),
which bid is submitted by a contractor which has performed no highway project
work for the department during the preceding five (5) years, unless the
department has determined that the contractor is prequalified to bid.
(B) A bid (or cost estimate) on any highway
project submitted by a contractor which is not prequalified or exempt from
prequalification under subsection (2)(A) of this rule shall not be accepted by
the department or commission. Acceptance by the department only occurs if the
highway project bid of the contractor is received, opened, and the total bid
publicly read by the department. If part of a combination bid is legally
acceptable and another portion is not (such as in permissive combinations which
are not qualified "All or none"), the department shall accept that portion
which was legally bid and shall not accept the rest. If the department
inadvertently errs in accepting a bid on a highway project which it should not
have accepted under this rule and section
227.105,
RSMo, the department, prior to any contract award, shall notify all contractors
which bid on that highway project and the commission of the erroneous
acceptance of the bid from a contractor which was not properly prequalified
under this rule, showing that the matter has been corrected, and that action
shall render null and void the prior erroneous bid acceptance.
(C) A contractor which is neither
prequalified nor exempt from qualification under this rule may be prequalified
by satisfying the specific criteria set forth below in section (4) of this
rule.
(D) Effective on or after
August 28, 1996, the fact that a contractor has a standard contractor
questionnaire on file with the department by the appropriate date does not
allow that contractor to bid on all highway projects. It only permits that
contractor to bid on those highway projects which have a cost estimated by the
contractor at two (2) million dollars or less, if that contractor has done no
work in the preceding five (5) years.
(4) Contractor Prequalification
Responsibility.
(A) contractor (which, with
reference to a partnership or joint venture, includes all component contractors
jointly and severally) which has performed no work for the department during
the preceding five (5) years must supply the following information to the
satisfaction of the department, on a prequalification contractor questionnaire
form obtained from the department, in order to become prequalified to bid on
any highway project with a completion cost estimated by the contractor through
its bid to be in excess of two (2) million dollars:
1. The same information required of any other
contractor on a standard contractor questionnaire form. The prequalification
contractor questionnaire form requests this information also. It is not
necessary for a contractor to complete both forms to be prequalified;
2. The type(s) of highway projects in which
the contractor desires to be prequalified. A contractor may apply to be
prequalified in any one (1), more than one (1), or all types of highway project
work. For the purposes of this rule, the various general highway project work
types are-
A. Earthwork, including excavation,
fill, grading, hauling, wasting, compaction and/or landscaping, including
signing and signaling and other related work;
B. Bituminous pavement, including signing and
signaling, guardrails, shoulders, and other related structures;
C. Portland cement concrete pavement,
including signing and signaling, guardrails, shoulders, and other related
structures;
D. Bridges, culverts
and other similar structures, including signing and signaling, guardrails,
shoulders, and other related structures; and
E. Other miscellaneous highway project types
of work (which the contractor must describe specifically);
3. The contractors experience in performing
the type(s) of highway project for which prequalification is requested. The
contractor must include the construction experience of the contractor's key
personnel necessary to complete the type(s) of highway project
designated;
4. The contractor's
ability to complete the type(s) of highway project that the contractor has
requested to be prequalified in. At a minimum, this shall include a showing of
the contractor's ability to complete highway projects in a timely manner, by
furnishing to the department a listing of all projects completed within the
last five (5) years similar to the type(s) of highway project that the
contractor requests prequalification on;
5. The type(s) of highway projects the
contractor is qualified to perform. This showing can be made by a signed and
notarized writing from the contractor's surety bonding company or broker,
stating the type(s) of highway projects (as designated above) for which that
company or broker will issue a performance and payment bond in an amount in
excess of two (2) million dollars, to cover the highway project work and debts
of that contractor;
6. Satisfactory
evidence of the contractor's current insurance coverage, including
comprehensive general liability, worker's compensation, and
automobile/vehicular coverage. The evidence of insurance shall, at a minimum,
demonstrate that the contractor has the same insurance required by the
commission of other contractors to perform construction work on a state highway
project. Or, the contractor and its insurance company or broker shall submit
notarized statements that the contractor is able to and shall obtain the
required types and amounts of insurance, with the required endorsements, prior
to commencing work if the contractor is awarded a Missouri state highway
project contract;
7. The
contractor's designation of a Missouri resident individual or firm as its agent
for the receipt of legal process. This designation must include the complete
name, street and mailing address and phone number of that designated
agent;
8. The contractor's listing
of all current work in progress, whether or not the work is a highway project.
This listing shall include the total value of all such work not yet completed,
and the contract and estimated actual completion dates of these
projects;
9. The equipment that the
contractor has available for the type(s) of highway project for which
prequalification is requested. For the purposes of this rule, equipment is
available if the contractor currently owns, rents or leases that equipment, or
if the contractor has the present ability to rent, lease or purchase such
equipment so that it is available for use on such designated type(s) of highway
project. The designation of available equipment shall include a specific list
of all classes of equipment available to perform the type(s) of highway project
work designated for prequalification, and whether they are currently owned,
leased, or available for rent, lease or purchase; and
10. Where practical, the contractor shall
provide from its highway project surety bonding company, copies of records from
the most recent audit issued of that company (and not the brokerage company
which merely sells the surety bonds issued by another company). Audit report
documents and records from independent public accounting or certified public
accountant (C.P.A.) firms are preferred, rather than internal bonding company
audits. This information should indicate the general financial stability of the
surety bonding company the contractor anticipates using to bond its highway
projects in Missouri. If the bonding company is listed in the "United States
Department of the Treasury, Fiscal Service, Department Circular 570, Companies
Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies" and is authorized to issue surety bonding
instruments in Missouri, only a photocopy of the bonding company's audit assets
and liabilities balance sheet is necessary. The department prefers that the
bonding company submit these audit record copies directly to the department. If
it is not practical to obtain or submit these documents from the surety bonding
company's most recent audit, a complete and detailed explanation of why it is
not practical to provide that information at present, when that information
will be provided to the department, or why that information is not necessary to
be provided, must be submitted in lieu thereof, with supporting documentation.
The department will determine if the justification for why it is not practical
to obtain or submit the bonding company audit information is
satisfactory.
(B)
Submitting the Prequalification Contractor Questionnaire to the Department.
1. The prequalification contractor
questionnaire must be completed fully and accurately, personally signed and
notarized, and mailed or delivered (including electronic means) to the
department so that it is received by the appropriate departmental staff no less
than seven (7) calendar days prior to the date and hour the contractor
anticipates bidding on any Missouri highway project. However, if the contractor
already has a standard contractor questionnaire on file with the department, it
may bid on any Missouri highway project which the contractor's bid estimates
will cost two (2) million dollars or below.
2. The prequalification contractor
questionnaire must be mailed or delivered to:
Division Engineer, Construction and Materials
Missouri Department of Transportation
1617 Missouri Boulevard
PO Box 270
Jefferson City, MO 65102-0270
(C) Delivery may be in person, by a
representative or agent, or by any United States Postal Service or express
delivery company, without restriction, or electronically, as long as it is
complete and received in the appropriate office of the department no later than
seven (7) calendar days prior to the date and hour the contractor's bid will be
opened by the department.
(D) If
the contractor fails to supply the form to the department within this specified
time frame, submits an incomplete form which lacks any necessary information
requested, or does not submit any form at all, the contractor shall not be
allowed to bid on any highway project (if no valid standard contractor
questionnaire is on file with the department). Additionally, the contractor
shall not be allowed to bid on any highway project which that contractor
estimates to cost in excess of two (2) million dollars.
(E) The contractor will be notified in
writing if the prequalification contractor questionnaire is incomplete or
insufficient in any respect. If practicable, notification will be made by
facsimile transmission as well as by first class United States mail, or
electronically, so that the contractor is aware of the problem prior to
submitting any highway project bid to the department.
(5) Departmental Review and Contractor
Prequalification.
(A) Once the department
receives the form from the contractor within the specified seven (7)-day time
period prior to the date and hour of the bid opening of the highway project,
the department will review the prequalification contractor questionnaire form
for accuracy and completeness, and will verify such information contained or
attached to the form as the department deems appropriate. The department's
review of the contractor's form will be conducted by the unit or staff
designated by the chief engineer in writing for that purpose.
(B) If, in the discretion of the designated
staff of the department, the contractor's prequalification contractor
questionnaire and attachments show that the contractor should be qualified to
bid on highway projects of the type(s) the contractor has requested
prequalification for, the department will notify the contractor in writing by
first class United States mail, and/or electronically. The department may also
notify the contractor by phone or facsimile transmission if a highway project
bid opening date is approaching, but there is no obligation upon the department
to do so. The contractor may also contact the department by phone, facsimile
transmission, or electronically, or in writing, to confirm that its
prequalification contractor questionnaire has been approved.
(C) If, in the discretion of the designated
staff of the department, the contractor's prequalification contractor
questionnaire and attachments do not show that the contractor is qualified to
bid on any one (1) or more of the type(s) of highway project for which the
contractor has requested prequalification, that departmental staff shall notify
the contractor applicant in writing, or electronically, that the application is
still undergoing review, and shall refer the matter to the chief engineer; or
if the chief engineer is unavailable, the assistant chief engineer; or if they
are unavailable, to the appropriate division engineer. That individual shall
make the final administrative decision on behalf of the department, as to
whether the contractor is or is not prequalified to bid on any or all types of
highway projects for which prequalification is requested. That individual shall
act no later than twenty-one (21) calendar days after the date the completed
prequalification contractor questionnaire with all attachments was
received.
(D) If a contractor is
dissatisfied with the final administrative decision made by the department on
its prequalification contractor questionnaire, the contractor may request in
writing, or electronically, within twenty-one (21) calendar days of the date of
mailing by the department of the administrative review that the commission
review the final administrative decision made by the department. A contractor
is not obligated to seek commission review in order to preserve its rights. Any
request for commission review shall be made to:
Commission Secretary
Missouri Highways and
Transportation Commission
105 West Capitol Avenue
PO Box 270
Jefferson City, MO 65102-0270
The request for review shall state specifically and
completely the legal and factual basis upon which the contractor believes its
prequal-ification application was denied in error. At the commission's sole
discretion, the commission shall decide if it wishes to review the final
departmental decision. If the commission elects to itself review that decision,
it shall make its review when it deems best, upon the records and documents in
the possession of the department. There will be no further briefing, personal
appearance, argument, or presentation to the commission by the contractor or
its representative, agent, or attorney. The commission's decision on that
record shall supersede the prior decision of the department, and shall then
constitute the final administrative decision. If the commission elects in its
sole discretion to not review the department's decision, then that departmental
decision shall stand as the final administrative decision.
(E) A contractor which was denied
pre-qualification to perform any type of highway project may reapply for
prequalification for that or other types of highway projects in sixty (60) days
or more from the date of the final administrative decision by the department
(or commission), or when the circumstances which caused the denial have changed
significantly, whichever is less. If the contractor reapplies on the basis of a
significant change of circumstances, a complete explanation and supporting
documentation showing the significant change of circumstances must be attached,
in addition to all other information and documentation required by this
rule.
(F) The department and
commission will not entertain appeals, requests for reconsideration, or other
objections from any third parties that a contractor was prequalified wrongfully
or improperly.
(6)
Effect of Contractor Prequalification.
(A) The
contractor shall be entitled to bid on all highway projects having a cost
estimated by the contractor below two (2) million dollars; and on those highway
projects having a cost estimated by the contractor in excess of two (2) million
dollars for which it is pre-qualified to bid by the final administrative
decision of the department (or where applicable, the commission). If the
contractor bids on any highway project having a cost estimate by that
contractor in excess of two (2) million dollars for which it has not been
prequalified, its bid may be rejected, subject to subsection (6)(B) of this
rule.
(B) If a contractor has a
valid standard contractor questionnaire or prequalification contractor
questionnaire on file with the department, and then does any highway project
work for the department or commission, the contractor is entitled to bid on any
highway project work without limitation or restriction. Any limitations on the
type or estimated cost of highway project work which previously applied to a
contractor which has any valid contractor questionnaire on file with the
department no longer apply when that contractor has completed any highway
project work for the department or commission within the five (5)-year period
prior to having its bid on a highway project opened. Further, a contractor who
has submitted a valid prequalification contractor questionnaire may bid on any
type of highway project, including those highway project types which the
department (or commission) did not pre-qualify that firm for, if the
contractor's bid or cost estimate of that highway project is not in excess of
two (2) million dollars.
(C) A
contractor remains prequalified, based upon its prequalification contractor
questionnaire, for a period of one (1) year. At that time, the contractor will
have up to three (3) months to refile another prequalification contractor
questionnaire (if it has not done any highway project work for the department
or commission in the last five (5) years before the contractor's bid will be
opened) if the contractor desires to bid on highway projects having a cost
estimate in excess of two (2) million dollars. However, the contractor may file
a standard contractor questionnaire if the contractor has done any work for the
department or commission within the five (5)-year period preceding the date of
bid opening of a highway project with a cost estimated by that contractor in
excess of two (2) million dollars which the contractor will bid on; or if the
contractor will not bid during the next year on a highway project having a cost
estimated by that contractor in excess of two (2) million dollars.
(D) A contractor which filed a valid and
acceptable prequalification contractor questionnaire, and then did any highway
project work for the department or commission, does not need to file another
contractor questionnaire form during the balance of the period in which that
prequalification contractor questionnaire remains valid. That contractor will
be viewed in all legal respects as if it had a standard contractor
questionnaire on file. Once a prequalification contractor questionnaire is
filed validly, it serves the same functions as a standard contractor
questionnaire for all purposes.
(E)
Any contractor which files a prequalification contractor questionnaire
unnecessarily, because it has done highway project work for the department or
commission within at least the last four (4) years, will not have the
questionnaire rejected for that reason. Instead, the contractor will be
informed in writing, or electronically, that its contractor questionnaire has
been accepted, and that the contractor could have filed a standard contractor
questionnaire instead.
(7) Miscellaneous Provisions.
(A) All information submitted by a
contractor, its bonding company or others to the department relevant to a
determination of minimum qualifications to bid under section
227.105,
RSMo, and all information used by the department to determine the contractor's
prequalification to bid under that statute and this rule, is protected from
disclosure pursuant to the provisions of that statute and section
610.021,
RSMo.
(B) The provisions of this
rule are intended to be severable. If any provision is found by a court of
competent jurisdiction to be invalid, unlawful, or unconstitutional, the
remaining provisions of the rule are intended to be valid unless the court
finds the valid provisions of the rule are so essentially and inseparably
connected with, and so dependent upon, the void provision that it cannot be
presumed the commission would have promulgated the valid provisions without the
void one; or unless the court finds that the valid provisions, standing alone,
are incomplete and are incapable of being executed in accordance with the
commission's intent or with section
227.105,
RSMo.
*Original authority: 226.130, RSMo 1939, amended 1993,
1995; 227.105, RSMo 1996.