Missouri Code of State Regulations
Title 7 - MISSOURI DEPARTMENT OF TRANSPORTATION
Division 10 - Missouri Highways and Transportation Commission
Chapter 10 - Contractor Performance Rating to Determine Responsibility
Section 7 CSR 10-10.070 - Procedure for Annual Rating of Contractors
Current through Register Vol. 49, No. 18, September 16, 2024
PURPOSE: This proposed amendment clarifies the actions available to a contractor upon receiving an unacceptable rating.
(1) Annual Rating of Contractors. The construction and materials division shall be responsible for the determination of the annual ratings of contractors. The construction and materials division will annually determine a contractor's overall and category performance rating for all contracts on all active projects. The performance ratings for the categories of "Quality of Work" and "Contract Compliance" will be based on a weighted average of the dollar value of all work completed during the rated year on all contracts. The performance ratings for the categories of "Prosecution and Progress" and "Contract Administration" will be based on a weighted average of the applicable contract dollar totals.
(2) Contractor Rating Groups. For purposes of recognizing outstanding contractor performance, contractors shall be divided into four (4) sample groups based upon whether the contractor is a specialty contractor and on the dollar value of the work completed during the rated year.
(3) Determination of Contractor Ratings. The construction and materials division shall determine contractor ratings and make action recommendations to the chief engineer.
(4) Review Process. If the contractor disagrees with any performance measure finding on the contractor performance project evaluation and cannot resolve the dispute with the resident engineer, it may request in writing that the district engineer review the matter. Such request must be made to the district engineer within twenty-eight (28) days from the date of the mailing of the project evaluation to the contractor. However, the contractor's representative shall first have discussed the project evaluation response with the resident engineer in order to resolve the dispute. Upon receiving the contractor's written request to review the disputed performance measure finding on the project evaluation, the district engineer shall review the matter and provide the contractor with a written response regarding the particular area of dispute between the contractor and the resident engineer. All reports shall be submitted to the construction and materials division before, but no later than, February 15.
(5) No Further Commission Action. As to contractor performance ratings of which no review is requested or permitted under this rule, upon the determination by the construction and materials division regarding the annual ratings of all contractors and the approval of the chief engineer of the annual ratings, the ratings of the contractors shall become final for purposes of this chapter and the effect of this chapter on a level of performance on the contractor's status to bid or perform work as a subcontractor or vendor on commission contracts. No commission action is necessary regarding the annual ratings of the contractors.