PURPOSE: This rule addresses the application requirement, issuing of permits and installation inspections for the repair, replacement or new installation of objects that are subject to the Act and these rules.
(1) As used in this rule, the term "these rules" is intended to mean 11 CSR 40-2.010
through 11 CSR 40-2.065.
(2) Effective January 1, 2007 an installation permit shall be obtained by the installer from the Division of Fire Safety, Boiler and Pressure Vessel Unit before the start of work for each new, second hand or reinstalled boiler, water heater or pressure vessel. Replacement or relocation of an existing boiler, water heater or pressure vessel shall be permitted as a new installation. The requirement to obtain an installation permit prior to the start of work is waived for an emergency replacement upon notification to the chief inspector.
(3) An application for an installation permit shall be submitted to the chief inspector on forms provided by the Division of Fire Safety, Boiler and Pressure Vessel Unit at least sixty (60) days prior to the start of the installation.
(4) Fees. | |
(A) Plan Review Hourly Fee | $ 35 |
(B) Installation Permit Fees- | |
1. Hot Water Heating Boiler- | |
A. 400,000 BTUH and less | $ 70 |
B. Greater than 400,000 BTUH but less than 12,500,000 BTUH | $175 |
C. 12,500,000 BTUH and above | $245 |
2. Hot Water Supply Boilers, Circulating Water Heaters, and Pool Heaters- | |
A. 400,000 BTUH and less | $ 70 |
B. Greater than 400,000 BTUH but less than 12,500,000 BTUH | $175 |
C. 12,500,000 BTUH and above | $245 |
3. Fired Jacketed Steam Kettles | $ 70 |
4. Power Boilers- | |
A. 400,000 BTUH and less | $ 70 |
B. Greater than 400,000 BTUH but less than 12,500,000 BTUH | $175 |
C. 12,500,000 BTUH and above | $245 |
5. Pressure Vessel- | |
A. 1,000 cu.ft. (7,500 gallons) or less | $ 70 |
B. Greater than 1,000 cu. ft. | $175 |
C. Compressed air receivers including tank mounted air compressors designed to operate at 250 psi or less and having a volume of 250 gallons or less | $ 25 |
D. Carbon Dioxide Storage Vessels used solely for carbonated beverage systems | $ 25 |
6. Steam Heating Boilers- | |
A. 400,000 BTUH or less | $ 70 |
B. Above 400,000 BTUH but less than 12,500,000 BTUH | $175 |
C. 12,500,000 BTUH and above | $245 |
7. Fired Storage Water Heaters (Above 200,000 BTUH or 120 gallons) | $ 70 |
(5) Upon completion of an installation the chief inspector or a deputy inspector shall perform a certificate inspection. After correcting any deficiencies noted during the certificate inspection and payment of the required fees the chief inspector will issue an Inspection Certificate.
(6) Any boiler, water heater or pressure vessel installed on or after January 1, 2007 without obtaining the required permit shall obtain an installation permit and correct any deficiencies identified during the certificate inspection before an Inspection Certificate can be issued. If additional inspections are required to confirm the adequacy of the required corrective actions the applicable inspection fees will be charged.
*Original authority: 650.215, RSMo 1984, amended 1990, 1993, 1995.