Rule 15-20-72-5.3.19 - Construction Phase Submissions, Approvals, and Actions -Timeline

Current through September 24, 2024

The following submittals, approvals, and actions will be required during the construction phase of the project. The Department may establish other time frames within the Grant agreement when properly justified.

1. Prior to payment of any reimbursement requests for construction contracts, the following shall be submitted and approved by the Department, as appropriate:

* Plans, specifications, contract documents

* Bid package, including procurement documentation

* Executed construction contract

2. By 50% completion of the last contract, Grant recipient shall submit a completed asset management plan for all drinking water facilities to be constructed in whole or in part with ARPA RWAI Grant funds.

3. By 90% completion of the last contract, the Grant recipient shall secure approval of the asset management plan.

4. Within 10 days after construction completion of each construction contract, the Grant recipient shall notify the Department of construction completion.

5. The Department will perform a final construction observation after the final contract has reached 90% completion. The final construction observation by the Department is only for the purpose of determining final Grant allowable costs.

6. Within 30 days after the current construction contract completion date, all change orders which include time extensions exceeding 30 days beyond the original contract completion date, and/or documentation showing the Grant recipient is implementing all legal remedies provided in the contract documents for failure to complete construction when required, shall be submitted to the Department for an allowability determination

7. Within 60 days of final contract completion, the Grant recipient shall submit: the final payment request for the awarded grant; approvable summary change orders for all construction contracts; full scale record drawings with all revisions shown and noted for the entire project funded in whole or in part with ARPA RWAI Grant funds; the licensed engineer's certification of compliance with plans, specifications, and contract documents; appropriate bacteriological test results; final construction phase professional services contract amendments, if any; and all other administrative forms and documents required by the Grant agreement.

8. Any other submittals or actions required by the Grant agreement shall be performed when so required and are subject to review and approval by the Department.

House Bill 1421, 2022 Regular Session & Senate Bill 2444, 2023 Regular Session of the MS Legislature

Disclaimer: These regulations may not be the most recent version. Mississippi may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.