Section 12-3-2.1-600 - PLANNING PROCEDURES
CONSTRUCTION DOCUMENT PHASE
Section 12-3-2.1-600.56 - AWARD OF CONTRACT

Current through September 24, 2024

Normally, the Bureau has forty-five (45) days after the bid opening to award a Contract. The exact days will be stated on the Proposal Form.

The Professional will prepare and submit a certified Bid Tabulation [See Appendix 600.] accompanied by a letter recommending an award to the Bureau and Using Agency. The Bureau will proceed as expeditiously as possible to present the award at the next PPRB meeting.

The Using Agency should notify its Governing Board of the award and the Governing Board should forward its confirmation to the Bureau as soon as possible.

The Professional, Using Agency and Governing Board will be informed in writing of the final action concerning the award made by the PPRB.

Disclaimer: These regulations may not be the most recent version. Mississippi may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.