Mississippi Administrative Code
Title 12 - Finance and Administration
Part 3 - Bureau of Building, Grounds and Real Property Management
Chapter 2 - Rules for the Bureau of Building, Grounds and Real Property Management
Rule 12-3-2.1 - Policies and Procedures
Section 12-3-2.1-600 - PLANNING PROCEDURES
CONSTRUCTION DOCUMENT PHASE
Section 12-3-2.1-600.23 - THE CONSTRUCTION DOCUMENTS

Current through September 24, 2024

Once the Bureau has approved the Design Development Phase, the Professional will prepare working Drawings and a Project Manual detailing specifications regarding the Work.

The Work

* Materials

* Workmanship

* Finishes

* Mechanical and electrical systems

* Asbestos abatement

* Special equipment

* Site work

* Utility connections and services

* Bidding information

* Proposals

* Contract and bond forms

* General, special and supplementary conditions of the Contract

* Other information required for receiving bids on the Project

Disclaimer: These regulations may not be the most recent version. Mississippi may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.