Once the Bureau has approved the Design Development Phase, the Professional will prepare working Drawings and a Project Manual detailing specifications regarding the Work.
The Work * Materials * Workmanship * Finishes * Mechanical and electrical systems * Asbestos abatement * Special equipment * Site work * Utility connections and services * Bidding information * Proposals * Contract and bond forms * General, special and supplementary conditions of the Contract * Other information required for receiving bids on the Project |
Disclaimer: These regulations may not be the most recent version. Mississippi may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.