Where Asbestos Containing Materials [ACM] must be
removed, the following guidelines and procedures have been developed to manage
this process:
A.
ASBESTOS CERTIFICATION
1. The
Professional is to secure the services of asbestos specialist(s) who possesses
current Project Designer and/or Project
Inspector certificate(s) issued by the Mississippi Department of
Environmental Quality's Office of Pollution Control.
2. A copy of each Certificate will be
attached to a comprehensive report submitted by the Professional to the Owner
defining the ACM present, its type, location and approximate
quantity.
3. If the Professional
has an asbestos specialist on staff who possesses proper certification, the
asbestos testing can be performed in house.
B.
SCHEDULE
1. Upon execution of the Standard
Form of Agreement Between the Owner and the Professional, the
Professional will submit a Schedule of Performance for
approval by the Bureau Staff. This Schedule will include
allowances for time required by the Bureau and Using Agency for review and
approval of the submissions. When the Schedule has been
approved by the Bureau, it will not, except for reasonable cause, be exceeded
by the Professional.
C.
ASBESTOS ABATEMENT PHASES
1.
Inspection/Sampling/Testing
2.
Abatement Document
3. Bidding
4. Abatement
D.
INSPECTION/SAMPLING/TESTING
PHASE
1. The Professional will consult
with the Owner to ascertain the applicable requirements of the Project.
2. The Professional shall perform
a complete inspection of the Project to determine:
a. Types of Asbestos
b. Locations of Asbestos
c. Quantities of Asbestos
3. The Professional will secure
the services of a testing laboratory qualified by the National Institute of
Safety and Health [NIOSH] to conduct tests. Services should include:
a. Sample Collection
b. Analysis
c. Reporting
4. The Professional, if qualified as a NIOSH
laboratory, may conduct the asbestos sampling, analysis and reporting.
5. The Owner will reimburse the
Professional for the testing required by this phase.
6. Four (4) copies of the comprehensive
written report will be submitted to the Owner. Documents should include:
a. Drawings
b. Testing Laboratory Reports
c. Cost Options
d. Owner's Options
7. The Professional will prepare and submit
an estimate of the Project's total cost. The estimate should include:
a. Costs associated with removal of ACM
b. Costs associated with disposal
of ACM
c. Replacement of any
finishes or materials disturbed during the removal process
d. Testing
e. Monitoring
8. The Professional will show progress to
date and confirm the remainder of the Schedule.
9. The Bureau must give written approval of
the Inspection/Sampling/Testing Phase before the Professional proceeds with the
next phase.
E.
ABATEMENT DOCUMENT PHASE
1.
(removed 7/9/09 per AG notification)
2. The Professional will prepare and submit
four (4) copies of Working drawings and specifications for approval. Two (2)
copies will be delivered to the Bureau and two (2) copies will be delivered to
the Using Agency. The drawings and specifications should detail and prescribe:
a. The Work to be accomplished.
b. Protective measures in accordance with EPA
guidelines.
c. Procedures for
shutting down mechanical and electrical systems.
d. Phasing of Work, if required.
e. Outlining responsibilities for cleaning.
f. Outlining responsibilities for
removing loose equipment.
3. After receiving a reviewed copy of the
Abatement Documents from the Owner, the Professional will review and revise the
documents. When the final revised copies are ready for distribution two (2)
copies will be given to the Owner and two (2) copies to the Using Agency prior
to release of documents for bids.
4. The Professional will provide complete
sets of plans, specifications, and other bidding documents for bidding
purposes.
a. The Professional will be
reimbursed for printing the bid documents by the Owner, with cost approval
prior to printing.
b. Costs of all
plans and specifications, other than for bidding, will be at the Professional's
expense.
5. The
Professional will prepare and submit to the Owner a detailed construction cost
analysis based on a quantity survey. The estimate will show an escalation
projected from the date of the estimate to the projected bid date.
6. The Professional will agree that approval
of the drawings and specifications by any person, body, or agency will not
relieve him of the responsibility for the adequacy, fitness, suitability,
correctness of design, and designing the Work in accordance with sound and
accepted practices and in compliance with prevailing building codes, federal
and state laws and regulations regarding asbestos abatement.
F.
BIDDING PHASE
1. Following the Owner's approval of the
Abatement Document Phase, the Professional will assist the Owner in:
a. Obtaining bids
b. Awarding a Contract
c. Preparing Construction Contracts
2. The Professional
will attend the bid opening and furnish a bid tabulation sheet in accordance
with the Bureau's format. [See Appendix 400.]
3. Immediately after receipt of bids, the
Professional will submit to the Owner a certified tabulation of all bids
received accompanied by a recommendation as to the award of Contract.
4. Following the award of
Contract, the Professional will prepare four (4) copies of updated construction
documents (specifications) and four (4) copies of reduced plans. Each copy will
be marked
OFFICIAL CONTRACT DOCUMENTS and will include:
a. Executed Bid Proposal Form (Photocopy is
acceptable)
b. Agreement Form
(With original signatures)
c.
Contract Bond (With original signatures)
d. Power of Attorney (No riders)
e. Insurance Certificates (Completed with no
alterations)
f. Bulletins,
addenda, and supplemental drawings
5. Reduced copies will be distributed as
follows:
a. Owner - two (2) copies.
b. Contractor - one (1) copy.
c. Professional - one (1) copy.
d. Owner's Representative - one
(1) copy.
6. The
Professional will provide the Attorney General's Special Counsel any
information required after the award of Contract.
G.
ABATEMENT PHASE
1. The Professional's relationship to the
General Contractor is outlined in the General Conditions of the Contract
between the Owner and the Contractor and is modified by any
Supplementary Conditions.
2. The Professional will perform the
following services during the Construction Phase:
a. Complete administration of all
construction Contracts
b. Issue
certificates for payment
c.
Examine and approve shop drawings and correct shop drawings when necessary for
conformance with the design intent
d. Make revisions, corrections, or
clarifications in the Contract Documents by bulletins or change orders,
together with all correspondence and clerical work in connection with bulletins
and change orders
e. Provide
sufficient on-site investigation to substantiate any of the above
f. Accept the completed Project, together
with such certificates, manuals, and guarantees as provided in the Contract
Documents
3. The
Professional will collect, maintain and house weekly payrolls from all
Contractors and Subcontractors for compliance with the labor standard
provisions in the Contract.
4. The
Professional will be responsible for conducting field inspections as needed.
a. The Professional will maintain a log of
all visits to the site by the Consultants and the Professional's firm
b. This log will be submitted once
a month to the Owner apprising the Owner of the progress and condition of the
Work
5. The
Professional will be the interpreter of the requirements of the Contract
Documents and judge of the performance thereunder of the Contractor.
6. The Professional will not issue any verbal
or written orders for omissions from, additions to, or changes in the
Construction Contract until approved in writing by the Owner.
7. The Professional will determine the
amounts owed to the Contractor based on inspections at the site and evaluations
of the Contractor's applications for payment.
8. The Professional will recommend, for the
Owner's approval, the issuance of certificates for payment in such amounts as
provided in the Contract Documents.
9. The issuance of certificates for payment
will not be a representation that the Professional has made any examination to
ascertain how and for what purpose the Contractor has used the monies paid on
account of the Contract sum, other than to secure certification under oath that
all Materialmen, Laborers, and Subcontractors have been paid by the Contractor.
10. Daily air monitoring and final
air clearance testing will be included in the Contractor's responsibility in
the Abatement Documents.
a. The Contractor
will select, supervise and pay for all job air monitoring
b. If for any reason, this is omitted from
the Contractor's responsibility, the Professional will provide the air
monitoring services without additional cost to the Owner
11. If the Asbestos Hazard Emergency Response
Act [AHERA] regulations require a final air clearance test by an independent
testing laboratory not associated with the Contractor, the Professional will
obtain that final test and the Owner will reimburse the Professional directly
for the expense of obtaining these services, provided the selection and costs
are preapproved by the Owner in writing.
12. The Professional and Consultants will
conduct a semi-final inspection when the Work has been completed.
a. When these items have been corrected by
the Contractor, the Professional, Consultants and Bureau Staff Inspector will
conduct a final inspection.
13. Upon completion of the Project, the
Professional will provide the Owner with two (2) sets of record documents which
include:
a. Changes caused by Addenda
b. Field changes
c. Change Orders
d. Observed changes by the Professional,
Contractor, or Subcontractors
14. The Professional will provide the
Attorney General's Special Counsel any information required at the end of the
Contract.
15. During the Warranty
period, the Professional will Work with the Owner's Representative to secure
remedies of defects that become apparent.
a.
The Professional will make, along with the Owner's Representative, a Warranty
inspection prior to the expiration of the Warranty period and report observed
discrepancies to the Contractor for correction
H.
PROFESSIONAL CONSULTING
SERVICES
1. If the Professional
renders basically abatement services, all plans, specifications, detailed
drawings and miscellaneous services required for architectural or engineering
Work will be accomplished by the Professional at no additional cost to the
Owner.