Mississippi Administrative Code
Title 12 - Finance and Administration
Part 3 - Bureau of Building, Grounds and Real Property Management
Chapter 2 - Rules for the Bureau of Building, Grounds and Real Property Management
Rule 12-3-2.1 - Policies and Procedures
Division 12-3-2.1-1 - GENERAL REQUIREMENTS
Section 12-3-2.1-1-01630 - SUBSTITUTIONS AND PRODUCT OPTIONS
Section 12-3-2.1-1-01630-1.04 - SUBSTITUTIONS
Universal Citation: MS Code of Rules 12-3-2.1-1-01630-1.04
Current through September 24, 2024
A. Professional will not consider requests for substitutions during bidding.
B. Within thirty (30) days after the Contract has been signed, the Professional will consider formal requests from the Contractor for substitution of products in place of those specified. Submit five (5) copies of the request for substitutions. Include in the request:
1. Complete data substantiating compliance of
proposed substitutions with Contract Documents.
2. For products:
a. Product identification including
Manufacturer's name and address.
b.
Manufacturer's literature: Product description, performance and test data and
reference standards.
c.
Samples.
d. Name and address of
similar products on which product was used and date of installation.
3. For construction methods:
a. Detailed description of proposed
method.
b. Drawings illustrating
methods.
4. Itemized
comparison of proposed substitutions with product or method
specified.
5. Data relating to
changes in construction schedule.
6. Accurate cost data on proposed
substitution in comparison with product or method specified.
C. In making request for substitution, Contractor represents:
1.
Proposed product, or method, has been investigated and determined that it is
equal or superior in all respects to that specified.
2. The same guarantee will be provided for
substitutions as for product or method specified.
3. Installation of accepted substitutions
will be coordinated into the Work, making such changes required of work to be
compete in all respects.
4. All
claims for additional costs related to substitution which consequently become
apparent will be waived.
5. Cost
data is complete and includes all related costs under the Contract.
D. Substitutions will not be considered if:
1. Indicated, or implied, on
shop drawings or product data submittals without formal request submitted in
accordance with this Section.
2.
Acceptance will require substantial revision of Contract Documents.
3. In the Professional's judgment, the
product, or material, is not equal.
Disclaimer: These regulations may not be the most recent version. Mississippi may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.