Mississippi Administrative Code
Title 12 - Finance and Administration
Part 3 - Bureau of Building, Grounds and Real Property Management
Chapter 2 - Rules for the Bureau of Building, Grounds and Real Property Management
Rule 12-3-2.1 - Policies and Procedures
Division 12-3-2.1-1 - GENERAL REQUIREMENTS
Section 12-3-2.1-1-01630 - SUBSTITUTIONS AND PRODUCT OPTIONS
Section 12-3-2.1-1-01630-1.04 - SUBSTITUTIONS

Current through September 24, 2024

A. Professional will not consider requests for substitutions during bidding.

B. Within thirty (30) days after the Contract has been signed, the Professional will consider formal requests from the Contractor for substitution of products in place of those specified. Submit five (5) copies of the request for substitutions. Include in the request:

1. Complete data substantiating compliance of proposed substitutions with Contract Documents.

2. For products:
a. Product identification including Manufacturer's name and address.

b. Manufacturer's literature: Product description, performance and test data and reference standards.

c. Samples.

d. Name and address of similar products on which product was used and date of installation.

3. For construction methods:
a. Detailed description of proposed method.

b. Drawings illustrating methods.

4. Itemized comparison of proposed substitutions with product or method specified.

5. Data relating to changes in construction schedule.

6. Accurate cost data on proposed substitution in comparison with product or method specified.

C. In making request for substitution, Contractor represents:

1. Proposed product, or method, has been investigated and determined that it is equal or superior in all respects to that specified.

2. The same guarantee will be provided for substitutions as for product or method specified.

3. Installation of accepted substitutions will be coordinated into the Work, making such changes required of work to be compete in all respects.

4. All claims for additional costs related to substitution which consequently become apparent will be waived.

5. Cost data is complete and includes all related costs under the Contract.

D. Substitutions will not be considered if:

1. Indicated, or implied, on shop drawings or product data submittals without formal request submitted in accordance with this Section.

2. Acceptance will require substantial revision of Contract Documents.

3. In the Professional's judgment, the product, or material, is not equal.

Disclaimer: These regulations may not be the most recent version. Mississippi may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.