Current through September 24, 2024
A. Scope: Submit to the Professional shop
drawings, product data and samples required by Specification sections. Submit
an additional copy of shop drawings, product data and samples related to
items/systems identified to be commissioned to the Commissioning Authority
Professional to be reviewed concurrently with the Professional. (if Cx on
project).
B. Shop Drawings:
Original drawings prepared by Contractor, Subcontractor, Supplier, or
Distributor which illustrate some portion of the Work; showing fabrication,
layout, setting, or erection details.
1.
Prepared by a qualified detailer.
2. Identify details by reference to sheet and
detail numbers shown on Contract drawings.
3. Minimum sheet size: 8 1/2" x 11"
4. Reproductions for submittals: Opaque diazo
prints.
C. Product Data:
1. Manufacturer's Standard Schematic
Drawings: Modify drawings to delete information which is not applicable to the
Project. Supplement standard information to provide additional information
applicable to the Project.
2.
Manufacturer's Catalog Sheets, Brochures, Diagrams, Schedules, Performance
Charts, Illustrations and Other Standard Descriptive Data: Clearly mark each
copy to identify pertinent materials, products, or models. Show dimensions and
clearances required. Show performance characteristics and capacities, wiring
diagrams and controls.
D. Samples: Physical examples to illustrate
materials, equipment or workmanship and to establish standard by which
completed work is judged.
1. Office Samples:
Of sufficient size and quantity to clearly illustrate functional
characteristics of products or material with integrally related parts and
attachment devices and full range of color samples. After review, samples
remain the property of the Professional until completion of the construction
project.
2. Field Samples and
Mock-ups: Erect on project site at location acceptable to Professional.
Construct each sample, or mock-up, completely including work of all trades
required in finished work.
E. Contractor's Responsibilities:
1. Review shop drawings, product data and
samples prior to submission.
2.
Verify field measurements, field construction criteria, catalog numbers and
similar data.
3. Coordinate each
submittal with requirements of work and of Contract Documents.
4. Contractor's responsibility for errors and
omissions in submittals is not relieved by the Professional's review of
submittals.
5. Contractor's
responsibility for deviations in submittals from requirements of Contract
Documents is not relieved by Professional's review of submittals unless
Professional gives written acceptance of specific deviations.
6. Notify Professional in writing at the time
of submission of deviations in submittals from requirements of Contract
Documents.
7. Begin no work
requiring submittals until the return of submittals bearing Professional's
stamp and initials, or signature indicating review.
8. After Professional's review, distribute
copies.
F. Submission
Requirements:
1. Schedule submission with
ample time before dates reviewed submittals will be needed.
2. Submit number of copies of shop drawings
and product data which Contractor requires for distribution, plus one (1) copy
to be retained by the Professional.
3. Submit number of samples specified in each
Specification section.
4. Accompany
submittals with transmittal letter, in duplicate, containing date, Project
title and number; Contractor's name and address; the number of each shop
drawings, product data and samples submitted; notification of deviations from
Contract Documents; and, other pertinent data.
5. Submittals shall include:
a. Date and revision dates.
b. Project title and number.
c. The names of the Professional, Contractor,
Supplier, Manufacturer and separate detailer, when pertinent.
d. Identification of product, or
material.
e. Relation to adjacent
structure, or materials.
f. Field
dimensions clearly identified as such.
g. Specification section number.
h. Applicable standards such as ASTM number,
or federal specifications.
i. A
blank space (2" x 3") for the Professional's stamp.
j. Identification of deviations from Contract
Documents.
k. Contractor's stamp,
initialed or signed, certifying the review of submittal, verification of field
measurements and compliance with Contract Documents.
G. Resubmission Requirements:
1. Shop Drawings: Revise initial drawings, as
required, and resubmit as specified for initial submittal. Indicate on the
drawings any changes which have been made other than those required by the
Professional.
2. Product Data and
Samples: Submit new data and samples, as required, for initial
submittal.
H.
Distribution of Submittals After Review:
1.
Distribute copies of shop drawings and product data which carry Professional's
stamp to Contractor's file, job site file, Subcontractor, Supplier and
Fabricator.
2. Distribute samples
as directed.
I.
Professional's Duties:
1. Review submittals
with reasonable promptness.
2.
Review for design concept of Project and information given in Contract
Documents.
3. Review of separate
item does not constitute review of an assembly in which item
functions.
4. Affix stamp and
initials, or signature, certifying the review of submittal.
5. Return submittals to Contractor for
distribution.