Section 12-3-2.1-1-01311 - NETWORK ANALYSIS SCHEDULE
Section 12-3-2.1-1-01311-1.05 - SCHEDULES

Current through September 24, 2024

A. Critical Path Methods: Prepare network analysis diagrams and supporting mathematical analyses using the Critical Path Method under Concepts and Methods as outlined in the AGC's The Use of CPM in Construction, A Manual for General Contractors and the Construction Industry.

B. Order of Work: Illustrate order and interdependence of activities and sequence of Work; how start of a given activity depends on completion of preceding activities, and how completion of the activity may restrain start of subsequent activities.

C. Complete Sequence of Construction: Illustrate complete sequence of construction by activity, identifying work of separate stages. Provide dates for submittals and return of submittals; dates for procurement and delivery of products; and dates for installation and provision for testing. Provide legend for symbols and abbreviations used.

D. Mathematical Analysis: Tabulate each activity of detailed network diagrams, using calendar dates, and identify for each activity:

1. Preceding and following event numbers

2. Activity description

3. Estimated duration of activity, in maximum thirty (30) day intervals

4. Earliest start date

5. Earliest finish date

6. Actual start date

7. Actual finish date

8. Latest start date

9. Latest finish date

10. Total and free float

11. Monetary value of activity (keyed to Schedule of Values)

12. Percentage of activity completed

13. Responsibility

E. Analysis Program: Capable of compiling monetary value of completed and partially completed activities, of accepting revised completion dates, and recomputation of all dates and floats.

F. Required Sorts: List activities in sorts or groups:

1. By preceding work item or event number from lowest to highest

2. By amount of float, then in order of early start

3. By responsibility in order of earliest possible start date

4. In order of latest allowable start dates

5. In order of latest allowable finish dates

6. Contractor's periodic payment request sorted by Schedule of Values listings, Specifications section

7. Listing of basic input data which generates the report

8. Listing of activities on the critical path

9. Monthly cash flow

G. Schedule of Values: Coordinate contents with Schedule of Values in Section 01300.

Disclaimer: These regulations may not be the most recent version. Mississippi may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.