Section 12-3-2.1-1-01311 - NETWORK ANALYSIS SCHEDULE
Section 12-3-2.1-1-01311-1.05 - SCHEDULES
Current through September 24, 2024
A. Critical Path Methods: Prepare network analysis diagrams and supporting mathematical analyses using the Critical Path Method under Concepts and Methods as outlined in the AGC's The Use of CPM in Construction, A Manual for General Contractors and the Construction Industry.
B. Order of Work: Illustrate order and interdependence of activities and sequence of Work; how start of a given activity depends on completion of preceding activities, and how completion of the activity may restrain start of subsequent activities.
C. Complete Sequence of Construction: Illustrate complete sequence of construction by activity, identifying work of separate stages. Provide dates for submittals and return of submittals; dates for procurement and delivery of products; and dates for installation and provision for testing. Provide legend for symbols and abbreviations used.
D. Mathematical Analysis: Tabulate each activity of detailed network diagrams, using calendar dates, and identify for each activity:
E. Analysis Program: Capable of compiling monetary value of completed and partially completed activities, of accepting revised completion dates, and recomputation of all dates and floats.
F. Required Sorts: List activities in sorts or groups:
G. Schedule of Values: Coordinate contents with Schedule of Values in Section 01300.