Section 12-3-2.1-1-01200 - PROJECT MEETINGS
Section 12-3-2.1-1-01200-1.01 - DESCRIPTION
Current through September 24, 2024
A. Contractor's Responsibilities: The General Contractor will administer all progress meetings which include the following:
B. Pre-Construction Meeting: The Bureau will schedule a pre-construction meeting as soon as possible after the award of Contract and the issuance of a Notice to Proceed.
C. Progress Meetings:
D. Commissioning Meetings: (if Cx on project) The Bureau will schedule a commissioning scoping meeting at the pre construction conference. Regular Commissioning Meetings will coincide with regularly scheduled Progress Meetings until such time that the Commissioning Process requires additional meetings. The Commissioning Authority Professional will chair, facilitate and document Commissioning Meetings.