A. General:
1. Coordination: Coordinate the work of all
Subcontractors and Material Suppliers.
2. Supervision: Supervise the activities of
every phase of work taking place on the Project.
3. Mechanical/Electrical: Take special care
to coordinate and supervise the work of the plumbing, heating and cooling and
electrical Subcontractors.
4.
Communication: Establish lines of authority and communication at the job
site.
5. Location: The Project
Coordinator must be present on the job all of the time.
6. Permits: Assist in obtaining building and
special permits required for construction.
B. Interpretations of Contract Documents:
1. Consultation: Consult with Architects and
Engineers to obtain interpretations.
2. Assistance: Assist in resolution of any
questions.
3. Transmission:
Transmit written interpretations to concerned parties.
C. Cessation of Work: Stop all work not in accordance with the requirements of the Contract Documents.
D. Division One: Coordinate and assist in the preparation of all requirements of Division One and specifically as follows:
1. Cutting and Patching: Supervise and
control all cutting and patching of other trades' work.
2. Project Meetings: Schedule and preside at
all project meetings.
3.
Construction Schedules: Prepare and submit all construction schedules;
supervise work to monitor compliance with schedules.
4. Shop Drawings, Product Data and Samples:
Administer the processing of all submittals required by the Project
Manual.
5. Schedule of Values:
Assist in preparation and be knowledgeable of each entry in the Schedule of
Values.
6. Testing: Coordinate all
required testing.
7. Temporary
Facilities and Controls: Allocate, maintain and monitor all temporary
facilities.
8. Substitutions and
Product Options: Administer the processing of all substitutions.
9. Project Closeout: Conduct final
inspections and assist in collection and preparation of closeout
documents.
10. Cleaning: Direct and
execute a continuing cleaning program throughout construction, requiring each
trade to dispose their own debris.
11. Project Record Documents: Maintain
up-to-date project record documents.
12. Safety Measures: Plan and enforce all
safety requirements.
E. Changes: Recommend and assist in the preparation of requests to the Professional for any changes in the Contract.
F. Application for Payment: Assist in the preparation and be knowledgeable of each entry in the Application and Certificate for Payment.
Disclaimer: These regulations may not be the most recent version. Mississippi may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.