Section 12-3-2.1-1-01028 - CHANGE ORDER PROCEDURES
Section 12-3-2.1-1-01028-1.02 - CHANGE ORDER PROCEDURES
Current through September 24, 2024
A. Change Proposed by Professional: The Professional may issue a Proposal Request to the Contractor which includes a detailed description of a proposed change with supplementary or revised Drawings and Specifications and a change in Contract Time for executing the change. The Contractor will prepare and submit an estimate within ten (10) days.
B. Change Proposed by Contractor: The Contractor may propose a change by submitting a request for change to the Professional, describing the proposed change and its full effect on the Work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation and a statement describing the effect on Work by separate or other Contractors. Document any requested substitutions in accordance with Section 01630 entitled Substitutions and Product Options.
C. Contractor's Documentation:
D. Construction Change Directive: The Professional may issue a document, approved by the Owner, instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. The document will describe changes in the Work, and will designate method of determining any change in Contract Sum or Contract Time. The change in Work will be promptly executed.
E. Format: The Professional will prepare five (5) originals of the Change Order using the Bureau of Building, Grounds and Real Property Management's Change Order Form. (see also 700.20)
F. Types of Change Orders:
G. Execution of Change Order: The Professional will issue Change Orders for signatures of parties as provided in the Standard Form of Agreement Between the Owner and the Contractor. Final execution of all Change Orders requires approval by the Owner.
H. Correlation of Contractor Submittals: The Contract shall promptly revise Schedule of Values and the Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust time for other items of Work affected by the change and resubmit. Promptly enter changes in Project Record Documents.