Section 12-3-2.1-1-01025 - SCHEDULE OF VALUES
Section 12-3-2.1-1-01025-1.01 - DESCRIPTION
Current through September 24, 2024
A. Scope: Submit a Schedule of Values to the Professional at least ten (10) days prior to submitting the first Application for Payment. Upon the Professional's request, the Contractor will provide supportive data substantiating their correctness. Use Schedule of Values only as basis for Contractor's Application for Payment.
B. Form of Submittal: Submit Schedule of Values on AIA Document G703, or computer generated form containing similar style, using Table of Contents of these Specifications as basis for format for listing costs of work for sections under Divisions 2-16. Identify each line item with number and title as listed in Table of Contents in these Specifications.
C. Preparing Schedule of Values:
D. Preparing Schedule of Unit Material Values:
E. Review and Resubmittal: After Professional's review, if requested, revise and resubmit Schedule of Values in same manner.