Part 4714.1108 - CONTROLLED-FLOW ROOF DRAINAGE
Universal Citation: MN Rules 4714.1108
Current through Register Vol. 48, No. 39, March 25, 2024
UPC section 1108.1 is amended to read as follows:
1108.1 Application. The controlled-flow roof drainage system shall be sized on the basis of controlled flow and storage of the storm water on the roof, provided the design is based on a minimum of 4 inches per hour and the following conditions are met:
(1) The water from a 25-year-frequency storm
shall not be stored on the roof for more than 24 hours.
(2) During the storm, the water depth on the
roof shall not exceed the depths specified in Table 1108.1 (2).
(3) Not less than two drains shall be
installed in roof areas of 10,000 square feet (929
m2) or less, and not less than one additional drain
shall be installed for each additional 10,000 square feet (929
m2 ) or less of roof area.
(4) Each roof drain shall have a
precalibrated, fixed (nonadjustable), and proportional weir (notched) in a
standing water collar inside the strainer. No mechanical devices or valves
shall be allowed.
(5) Pipe sizing
shall be based on the precalibrated rate of flow (gpm) (L/s) of the
precalibrated weir for the maximum allowable water depth, and Tables 1101.7 and
1101.11.
(6) The height of stones
or other granular material above the waterproofed surface shall not be
considered in water depth measurement, and the roof surface in the vicinity of
the drain shall not be recessed to create a reservoir.
(7) Roof design, where controlled-flow roof
drainage is used, shall be such that the design roof live load is not less than
40 lb/ft2.
(8) Scuppers shall be provided in parapet
walls. The distance of scupper bottoms above the roof level at the drains shall
not exceed the maximum distances specified in Table 1108.1(8).
(9) Scupper openings shall be not less than 4
inches (102 mm) high and have a width equal to the circumference of the roof
drain required for the area served, sized in accordance with Table
1101.11.
(10) Flashings shall
extend above the top of the scuppers.
(11) At a wall or parapet, 45-degree (0.79
rad) cants shall be installed.
(12)
Separate storm and sanitary drainage systems shall be provided within the
building.
(13) Calculations for the
roof drainage system shall be submitted, along with the plans, to the Authority
Having Jurisdiction for approval.
UPC Table 1108.1(2) and Table 1108.1(8) are not amended.
Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.