Minnesota Administrative Rules
Agency 183 - Water and Soil Resources Board
Chapter 8420 - WETLAND CONSERVATION
WETLAND BANKING
Part 8420.0820 - LOCAL GOVERNMENT UNIT MONITORING RESPONSIBILITIES
Universal Citation: MN Rules 8420.0820
Current through Register Vol. 49, No. 27, December 30, 2024
Subpart 1. Monitoring oversight.
A. The local government unit must evaluate
all monitoring reports for compliance with report requirements and must
determine if the goals of the approved plan can be met within the specified
monitoring period based on the current condition of the replacement wetland and
the applicant's proposed management activities for the following growing
season.
B. For project-specific
replacement, if the local government unit determines that the goals of the
approved replacement plan will not be met, it must take one or more of the
following actions:
(1) order specific
corrective actions on the replacement wetlands;
(2) order the applicant to prepare and
implement a new or revised replacement plan;
(3) request the enforcement authority to
issue a cease and desist order on the wetland impact activity if it has not
been completed;
(4) request the
local soil and water conservation district and enforcement authority to order
restoration of the impacted wetland;
(5) use any financial assurance collected
from the applicant to replace the lost wetland function and value;
(6) pursue a district court order requiring
the applicant to fulfill the replacement plan; or
(7) other actions that the local government
unit determines necessary to achieve the goals of the replacement
plan.
C. If the
landowner fails to submit the annual report associated with a project-specific
replacement plan in accordance with part
8420.0810, the local government
unit responsible for monitoring oversight must either pursue enforcement
actions under item B or prepare the annual report for the applicant. The local
government unit may charge fees for preparing the report or use any financial
assurance the applicant had provided to complete monitoring
requirements.
Subp. 2. Certification of successful replacement and completion of monitoring.
Upon completion of the minimum monitoring period, the applicant may request a field review by the local government unit and technical evaluation panel of the success of the replacement wetland. If the replacement is determined successful, the local government unit must provide written notification to the applicant that the replacement has been certified and the monitoring requirements have been fulfilled.
Statutory Authority: MS s 103G.2242
Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.