Minnesota Administrative Rules
Agency 174 - Pipeline Saftey Office
Chapter 7560 - EXCAVATION NOTICE SYSTEM
Part 7560.0150 - PUBLIC RIGHT-OF-WAY MAPPING AND INSTALLATION

Universal Citation: MN Rules 7560.0150

Current through Register Vol. 48, No. 39, March 25, 2024

Subpart 1. Duty of operator to map.

After December 31, 2005, an operator shall maintain a map, a diagram, a drawing, or geospatial information regarding the location of its underground facility within a public right-of-way installed after that date.

Subp. 2. Duty to install locating wire.

After December 31, 2005, an operator shall install a locating wire or have an equally effective means of marking the location of each nonconductive underground facility within a public right-of-way installed after that date. This requirement does not apply when making minor repairs to an existing nonconductive facility. As applied to this chapter, "minor repairs" means repairs to or partial replacement of portions of existing service laterals located within a public right-of-way for purposes of routine maintenance and upkeep.

Statutory Authority: MS s 299J.04

Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.