Part 7090.3010 - INDUSTRIAL ACTIVITY PERMIT REQUIREMENTS
Universal Citation: MN Rules 7090.3010
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Permits required.
An NPDES/SDS industrial storm water permit is required:
A. for industrial activity; or
B. if the commissioner determines that a
discharge may cause or contribute to a violation of an applicable state or
federal water quality rule or regulation. In making this determination, the
commissioner shall consider factors including size of discharge, quantity and
nature of discharge, and location of discharge.
Subp. 2. Permit application deadline.
If a person proposes to construct a new facility or engage in a new activity for which a permit is required, the person shall submit a complete permit application at least 180 days before the planned date of the commencement of facility construction or of the planned date of the commencement of the activity, whichever occurs first.
Statutory Authority: MS s 115.03
Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.