Minnesota Administrative Rules
Agency 167 - Pollution Control Agency
Chapter 7080 - INDIVIDUAL SUBSURFACE SEWAGE TREATMENT SYSTEMS
Part 7080.2220 - MOUNDS
Universal Citation: MN Rules 7080.2220
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Mound system requirements.
To qualify as a mound system, the system must meet or exceed the following requirements:
A. employ
flow values in parts
7080.1850 to
7080.1885;
B. meet or exceed applicable technical
requirements of parts
7080.1900 to
7080.2030,
7080.2050, and
7080.2100;
C. meet or exceed the requirements of part
7080.2150, subparts
2 and
3;
D. employ flow measurement; and
E. meet the requirements of subparts
2 and
3.
Subp. 2. Location of mounds.
A. The upper 12 inches of the original soil
mound absorption area must have a mound absorption ratio of greater than zero
under part
7080.2150, subpart
3, item E, Table IX or IXa.
The upper 12 inches of the absorption area must also be above the periodically
saturated soil or bedrock.
B.
Setbacks must be according to Table VII in part
7080.2150, subpart
2, item F. Setbacks must be
measured from the original soil absorption area.
C. On slopes of one percent or greater and
where the original soil mound absorption ratio is 5.0 or greater in Table IX or
IXa in part
7080.2150, subpart
3, item E, mounds must not be
located where the ground surface contour lines that lie directly below the long
axis of the distribution media bed represent a swale or draw, unless the
contour lines have a radius of curvature greater than 100 feet. Mounds must
never be located in swales or draws where the radius of curvature of the
contour lines is less than 50 feet.
Subp. 3. Mound design and construction.
A. The mound distribution
media bed area consists of bottom area only and must be calculated by dividing
the design flow by 1.2 gallons per square foot per day.
B. Mound distribution media beds must be
determined according to part
7080.2150, subpart
3, item M, and must be no
wider than ten feet.
C. Clean sand
must be used to elevate the mound distribution media bed and must consist of
sound, durable material that conforms to the following requirements:
Sieve Size | Percent Passing |
No. 4 | 95-100 |
No. 8 | 80-100 |
No. 10 | 0-100 |
No. 40 | 0-100 |
No. 60 | 0-40 |
No. 200 | 0-5 |
Clean sand must also contain less than three percent deleterious substances and be free of organic impurities.
D. The original soil mound absorption area is
determined by multiplying the original soil mound absorption length by the
original soil mound absorption width. The original soil mound absorption width
is calculated by multiplying the mound distribution media bed width by the
mound absorption ratio. The mound absorption ratio of the upper 12 inches of
soil in the proposed original soil mound absorption area shall be determined
according to Table IX or IXa in part
7080.2150, subpart
3, item E.
E. The required original soil absorption
width for mounds constructed on slopes from zero to one percent must be
centered under the mound distribution media bed width. The required original
mound soil absorption width constructed on slopes greater than one percent must
be measured downslope from the upslope edge of the mound distribution media bed
width and measured in the direction of the original land slope and
perpendicular to the original contours.
F. The side slopes on the mound must not be
steeper than three horizontal units to one vertical unit and shall extend
beyond the required original soil absorption area, if necessary.
G. Distribution of effluent over the mound
distribution media bed must be by level perforated pipe under pressure
according to parts
7080.2050 and
7080.2100.
H. The supply pipe from the pump to the
original soil absorption area must be installed before surface preparation of
the original mound soil absorption area. The trench excavated for the supply
pipe must be carefully backfilled and compacted to prevent seepage of
effluent.
I. Vegetation in excess
of two inches in length and dead organic debris including leaf mats must be
removed from the original soil mound absorption area. Trees must be cut nearly
flush with the ground and stumps must not be removed.
J. The original soil mound absorption area
must be roughened by backhoe teeth, moldboard, or chisel plow. The soil must be
roughened to a depth of eight inches. Discing is allowed if the upper eight
inches of soil has a texture of sandy loam or coarser. If plowed, furrows must
be thrown uphill and there must not be a dead furrow in the original soil mound
absorption area. A rubber-tired tractor is allowed for plowing or discing.
Rototilling or pulverizing the soil is not allowed. The original soil must not
be excavated or moved more than one foot from its original location during soil
surface preparation.
K. Prior to
placement of six inches of clean sand, vehicles must not be driven on the
original soil mound absorption area before or after the surface preparation is
completed. The clean sand must immediately be placed on the prepared
surface.
L. The clean sand must be
placed by using a construction technique that minimizes compaction. If the
clean sand is driven on for construction, a crawler or track-type tractor must
be used. At least six inches of sand must be kept beneath equipment to minimize
compaction of the prepared surface.
M. A minimum of 12 inches of clean sand must
be placed in contact with the bottom area of the mound distribution media bed
and must be uniformly tapered to cover the entire original soil absorption
area. Other sandy materials are allowed to be used outside of this area to
complete construction of the mound.
N. The top of the clean sand layer upon which
the mound distribution media bed is placed must be level in all
directions.
O. A vertical
inspection pipe at least four inches in diameter must be installed and secured
at the distribution medium and sand interface. The inspection pipe must have
three-eighths inch or larger perforations spaced vertically no more than six
inches apart. At least two perforations must be located in the distribution
medium. Perforations must not be located above the permeable synthetic fabric,
if used. The inspection pipe must extend to the bottom of the distribution
medium, be secured, and be capped, flush with or above finished
grade.
P. On slopes of one percent
or greater, the upslope edge of the mound absorption bed must be placed on the
contour.
Q. The sidewalls of the
mound absorption bed must be as vertical as practical and not intentionally
sloped.
R. The top of the mound
distribution media bed must be level in all directions.
S. A minimum of six inches of sandy to loamy
soil material must be placed on the top of the mound absorption bed and sloped
upwards toward the center of the mound a minimum of ten horizontal units to one
vertical unit.
T. Construction
vehicles must not be allowed on the distribution media until backfill is placed
as described in item S.
U. A
minimum of six inches of topsoil borrow must be placed over the entire
mound.
Statutory Authority: MS s 115.03; 115.55
Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.