Part 7077.0286 - COMPLETION OF CONSTRUCTION AND INITIATION OF OPERATION; WASTEWATER TREATMENT SYSTEMS
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Construction reporting requirements.
At least 60 days before the scheduled initiation of operation, the municipality shall submit to the commissioner, as appropriate:
Subp. 2. Prefinal inspection.
The municipality must notify the commissioner in writing when it is ready to initiate operation and request that a prefinal inspection be scheduled before initiation of operation can occur. The purpose of this inspection is to identify construction deficiencies and to set target dates for completion of construction items.
Subp. 3. Initiation of operation.
Subp. 4. Final inspection.
A final inspection of the wastewater treatment system shall be performed by agency staff when all the construction is complete except for minor weather-related components. The purpose of the inspection is to verify that construction is complete and conforms with the approved plans and specifications and change orders. The municipality shall request that a final inspection be performed when it believes construction is complete.
Statutory Authority: MS s 116.182; 446A.07