Current through Register Vol. 49, No. 27, December 30, 2024
Subpart
1.
Requirements.
To receive project certification under part
7077.0281, a municipality must
submit to the commissioner for review and approval the items under subparts
2 and
4 that are applicable to the
project. These items must be submitted within six months from the date that the
authority approves an intended use plan which includes the project for which
the municipality seeks certification.
Subp. 2.
Planning and design
projects.
Municipalities seeking certification for planning and design
projects shall submit:
A. a
description of the scope of work and estimated costs that will lead to an
approved facilities plan or storm water project plan;
B. a schedule for completion of the
facilities plan or the storm water project plan on a form prescribed by the
commissioner;
C. for wastewater and
storm water treatment projects, a schedule for completion of plans and
specifications; and
D. for
individual sewage treatment system projects, a copy of a draft ordinance that
adopts the requirements of chapter 7080, individual sewage treatment
standards.
Subp. 3.
[Repealed, 30 SR 923]
Subp. 4.
Construction projects.
Municipalities seeking certification for construction
projects shall submit:
A. for
wastewater treatment systems, plans and specifications as required under part
7077.0274 for the commissioner's
review and approval;
B. for
wastewater treatment systems, a certification that the municipality has enacted
an ordinance that, at a minimum:
(1)
prohibits new inflow connections to be added to the wastewater treatment
system;
(2) requires new sewers and
connections to be properly designed and constructed; and
(3) prohibits toxics and other pollutants to
be placed in the municipal wastewater treatment system in amounts or
concentrations that endanger public safety or the physical integrity of the
treatment system or cause exceedance of permit limitations;
C. for individual sewage treatment
system projects, a certification that the municipality has enacted and is
enforcing an ordinance that:
(1) adopts the
requirements of chapter 7080;
(2)
prohibits nonsewage discharges from nonresidential structures with wastewater
flows or nonsewage discharges from residential structures with a water-using
business to individual sewage treatment systems; and
(3) establishes a maintenance plan;
and
D. for storm water
treatment systems:
(1) plans and
specifications as required under part
7077.0279 for the commissioner's
review and approval;
(2) a project
schedule on a form prescribed by the commissioner; and
(3) if applicable, finalized and executed
intermunicipal agreements necessary for the successful implementation and
administration of the project.
Subp. 5. [Repealed, 30 SR 923]