Minnesota Administrative Rules
Agency 167 - Pollution Control Agency
Chapter 7045 - HAZARDOUS WASTE
FACILITY STANDARDS
Part 7045.0486 - CLOSURE
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Scope.
Except as part 7045.0450 provides otherwise, the provisions of subparts 2 to 6 and part 7045.0488 apply to the owner or operator of a hazardous waste facility.
Subp. 2. Closure performance standard.
The owner or operator shall close the facility in a manner minimizing the need for further maintenance. Closure procedures must result in controlling, minimizing, or eliminating, to the extent necessary to protect human health and the environment, postclosure escape of hazardous waste, hazardous constituents, leachate, contaminated runoff, or hazardous waste decomposition products to the ground or surface waters or to the atmosphere, in accordance with the closure requirements, including the requirements of parts 7045.0526, subpart 9; 7045.0528, subpart 9; 7045.0532, subpart 7; 7045.0534, subpart 7; 7045.0536, subpart 8; 7045.0538, subpart 7; 7045.0539, subparts 2 to 4; and 7045.0542, subpart 8; and Code of Federal Regulations, title 40, section 264.1102, as incorporated in part 7045.0550.
Subp. 3. Submittal and contents of closure plan.
The owner or operator of a hazardous waste facility shall submit a closure plan with the permit application, and the closure plan must be approved by the agency as part of the permit issuance procedure. The approved closure plan shall become a condition of any permit. The agency's approval must ensure that the approved closure plan is consistent with subparts 2, 4, and 5; parts 7045.0484, groundwater protection, and 7045.0488, closure activities; and the applicable closure requirements of parts 7045.0526, subpart 9; 7045.0528, subpart 9; 7045.0532, subpart 7; 7045.0534, subpart 7; 7045.0536, subpart 8; 7045.0538, subpart 7; 7045.0539, subpart 2; 7045.0542, subpart 8; and Code of Federal Regulations, title 40, section 264.1102, as incorporated in part 7045.0550.
A copy of the approved closure plan and all revisions to the plan must be furnished to the commissioner upon request, including request by mail, until final closure is completed and certified. The plan must identify steps necessary to completely or partially close the facility at any point during its intended operating life and to completely close the facility at the end of its intended operating life. The closure plan must at least include all of the following:
Subp. 4. Amendment of plan.
The owner or operator must submit a written request to the commissioner for a permit modification to authorize a change in operating plans, facility design, or the approved closure plan in accordance with the agency's permitting procedures in chapter 7001. The written request must include a copy of the closure plan amendments for approval. The owner or operator may request a permit modification to amend the closure plan at any time before notification of partial or final closure of the facility. The owner or operator shall request a permit modification to amend the plan whenever:
The commissioner may request modifications to the plan under the conditions described in items A to C. The owner or operator must submit the modified plan within 60 days of the commissioner's request, or within 30 days if the change in facility conditions occurs during partial or final closure. Any modifications requested by the commissioner will be approved in accordance with the agency's permitting procedures in chapter 7001. The owner or operator must submit a written request for a permit modification including a copy of the amended closure plan for approval at least 60 days before the proposed change in facility design or operation, or no later than 60 days after an unexpected event has occurred which has affected the closure plan. If an unexpected event occurs during the partial or final closure period, the owner or operator must request a permit modification no later than 30 days after the unexpected event.
Subp. 5. Notification of partial and final closure.
For units meeting the requirements of part 7045.0488, subpart 2a, the date on which the owner or operator expects to begin closure must be no later than 30 days after the date on which the hazardous waste management unit receives the known final volume of nonhazardous wastes, or if there is a reasonable possibility that the hazardous wastes management unit will receive additional nonhazardous wastes, no later than one year after the date on which the unit received the most recent volume of nonhazardous wastes. If the owner or operator can demonstrate to the commissioner that the hazardous waste management unit has the capacity to receive additional nonhazardous wastes and the owner or operator has taken, and will continue to take, all steps to prevent threats to human health and the environment, including compliance with all applicable permit requirements, the commissioner shall approve an extension to this one-year limit.
If the facility's permit or interim status is terminated, or if the facility is otherwise ordered by judicial decree or compliance order to cease receiving hazardous waste or to close, then the requirement in this item does not apply. However, the owner or operator shall close the facility in accordance with established deadlines.
Subp. 6. Removal of wastes and decontamination or dismantling of equipment.
Nothing in this part precludes the owner or operator from removing hazardous wastes and decontaminating or dismantling equipment in accordance with the approved closure plan at any time before or after notification of partial or final closure.
Statutory Authority: MS s 14.07; 116.07