Minnesota Administrative Rules
Agency 167 - Pollution Control Agency
Chapter 7041 - SEWAGE SLUDGE MANAGEMENT
Part 7041.0800 - APPLICATION AND APPROVAL PROCEDURE FOR LAND APPLICATION SITES
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Site application.
Persons who are required by part 7041.0600, subpart 3, to obtain a site approval from the commissioner must apply for the approval as provided in this part. Applications for approvals must be completed and signed by a Type IV certified operator or inspector. An approval is only valid for the conditions stated in the approval, including management practices and acreage authorized. If a change in acreage is proposed, a new application must be submitted and approval obtained. If a change in management practices included in the site approval is proposed, the change shall be authorized by the commissioner through a letter to the person who applies for the change before the person initiates the change.
The application must include a copy of the notification described in subpart 6 and the specific information given in subparts 2 to 5 submitted on a site application form obtained from or approved by the commissioner.
Subp. 2. Site characterization.
Site applications must contain site characterization that includes the following:
Subp. 3. Site management.
Applications must include site management, including:
Subp. 4. Application requirements for long-term storage of dewatered bulk sewage sludge at the site at which the bulk sewage sludge is applied.
Applications must include the following information if approval of long-term storage at the land application site is requested:
Subp. 5. Modification of management practices.
If any modification of the suitable soil conditions, slopes, or separation distances in part 7041.1200, subpart 3, are requested for nonagricultural uses, the site application must indicate what the nonagricultural use is; which conditions, slopes, or separation distances should be modified; and what environmental benefits will result from bulk sewage sludge application under the proposed conditions.
Subp. 6. Approval procedure; public notification.
Persons who prepare bulk sewage sludge shall provide notice by mail of the proposed land application site on the same date to the commissioner, the owner and occupier of the site, the city or township and county official of the area where the land application site is located, and any person known by the preparer to be interested in the approval of the site. The notice must include:
Subp. 7. Review.
Applications shall be reviewed for completeness by the commissioner. If the application is incomplete, the commissioner shall promptly advise the applicant of the incompleteness. Further processing of the application shall be suspended until the applicant has supplied the necessary information to the commissioner.
Subp. 8. Approval or denial.
Notice of approval or denial and reasons for a denial shall be issued by the commissioner to the persons listed in subpart 6 no sooner than 30 days from the date the notification of the land application site was sent to those persons.
Subp. 9. Final determination.
The commissioner shall attempt to resolve all comments prior to a final determination concerning the application. If the comments have been resolved, the commissioner shall issue or deny the approval. If all comments cannot be resolved, the application shall be presented to the agency board, which shall issue or deny the approval.
Subp. 10. Enforcement.
A site approval issued to the person who prepares sewage sludge under this part shall be enforceable to the same extent and in the same manner as a permit.
Subp. 11. Revocation of site approvals.
A site approval may be revoked in accordance with the requirements of part 7001.0170.
Statutory Authority: MS s 116.07