Minnesota Administrative Rules
Agency 167 - Pollution Control Agency
Chapter 7002 - PERMIT FEES
WATER QUALITY PERMIT FEES
Part 7002.0253 - WATER QUALITY PERMIT APPLICATION FEES AND ADDITIONAL FEES
Universal Citation: MN Rules 7002.0253
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Application points.
The points assessed for each permit application, amendment, or water quality effluent limitation review designated in this subpart shall be multiplied by the dollar per point value as determined in part 7002.0252 to calculate the application fee.
A. A person
requesting a water quality effluent limitation review shall pay a fee equal to
five points for each preliminary effluent limit request submitted in advance of
or separate from an NPDES/SDS permit application. If multiple requests for
reviews are submitted to the agency over time, each request is subject to the
fee.
B. A person submitting an
application for a feedlot permit shall be assessed as follows:
(1) for coverage under a general feedlot
permit to construct or operate, a fee equivalent to two points;
(2) for modification of activities under a
general feedlot permit, a fee equivalent to two points;
(3) for issuance of an individual feedlot
permit to construct or modify, a fee equivalent to six points; and
(4) for reissuance of an individual feedlot
permit, a fee equivalent to two points.
C. A person submitting an application for
discharge of wastewater, operation of a disposal system, or biosolids treatment
or storage shall be assessed as follows:
(1)
for coverage under or modification of a general permit to construct or operate,
a fee equivalent to four points;
(2) for issuance of an individual wastewater
permit or biosolids treatment or storage permit for a new facility, a fee
equivalent to 30 points;
(3) for a
major modification with no construction, a fee equivalent to eight
points;
(4) for a major
modification with construction but with no increase in design flow, a fee
equivalent to eight points;
(5) for
a major modification with construction and an increase in design flow, a fee
equivalent to 30 points;
(6) for a
minor modification requested by the permittee and not for the purpose of
correcting permit errors, a fee equivalent to four points;
(7) for reissuance of an individual permit,
with no modifications requested by the permittee, a fee equivalent to four
points;
(8) for issuance of an
individual pretreatment permit, a fee equivalent to eight points; and
(9) for issuance of an individual dredge
material disposal permit, a fee equivalent to eight points.
D. A person submitting an
application for a sewer extension shall be assessed based on the additional
design flow as follows:
(1) to increase flows
from 0 to 0.10 million gallons per day (MGD), a fee equivalent to one
point;
(2) to increase flows from
greater than 0.10 to 1.0 MGD, a fee equivalent to two points; and
(3) to increase flows greater than 1.0 MGD, a
fee equivalent to three points.
Subp. 2. Additional points.
The points assessed for activities designated in this subpart shall be multiplied by the dollar per point value as determined in part 7002.0252 to calculate the additional fee.
A. A person submitting
an individual permit application under subpart
1 with a new or increased
maximum daily design flow for an industrial facility, or average wet weather
design flow for all other facilities, shall be assessed a fee according to this
item. The flow determination does not include noncontact cooling water, which
is assessed points under item B:
(1) if the
resulting flow increase is 0 to 0.20 MGD, no additional fee shall be
assessed;
(2) if the resulting flow
increase is greater than 0.20 MGD and less than 1.0 MGD, a fee equivalent to
five points;
(3) if the resulting
flow increase is equal to or greater than 1.0 MGD and less than 5 MGD, a fee
equivalent to ten points;
(4) if
the resulting flow increase is equal to or greater than 5 MGD and less than 20
MGD, a fee equivalent to 20 points;
(5) if the resulting flow increase is equal
to or greater than 20 MGD and less than 50 MGD, a fee equivalent to 30
points;
(6) if the resulting flow
increase is equal to or greater than 50 MGD, a fee equivalent to 40 points;
and
(7) if the resulting flow is
from mine pit or quarry dewatering or sewer extensions, no additional fee shall
be assessed.
B. A person
submitting an application for an individual permit that includes the discharge
of noncontact cooling water shall be assessed a fee based on the increased
maximum daily design flow resulting from new or modified noncontact cooling
water discharge as follows:
(1) if the
resulting increase in flow is less than 50 MGD, a fee equivalent to five
points; and
(2) if the resulting
increase in flow is equal to or greater than 50 MGD, a fee equivalent to 20
points.
C. If a permit
application requires a nondegradation review under parts
7050.0250 to
7050.0335,
7050.0186, or
7052.0300 to
7052.0330, the applicant shall pay
a fee equivalent to 20 points.
D.
If a permit applicant requests a variance under part
7000.7000, the applicant shall pay
a fee equivalent to 35 points.
E.
If a person makes a confidentiality request under part
7000.1300, the applicant shall pay
a fee equivalent to two points. This fee applies regardless of whether it is
requested as part of a permit application.
F. If an EAW is required under a mandatory
category specified in part
4410.4300, the agency is the
designated responsible governmental unit (RGU), and an air or water permit is
required for the project, the applicant shall pay fees as described in subitems
(1) to (3). If a facility requires both an air and water permit, the points for
an EAW review shall be assessed only once. The agency shall use the lower of
the dollar per point value for an air or water permit as calculated in part
7002.0018 or
7002.0252 to calculate the fee.
Fees shall be assessed as follows:
(1) if an
applicant is required to complete an EAW under part
4410.4300, subpart 18, item A, or
29, a fee equivalent to 15 points;
(2) if an applicant is required to complete
an EAW under part
4410.4300, subpart 8, item A or B;
10, items A to C; 16, item A or D; 17, items A to C or E to G; or 18, item B or
C, a fee equivalent to 35 points; and
(3) if an applicant is required to complete
an EAW under part
4410.4300, subpart 4; 5, item A or
B; 13; 15; 16, item B or C; or 17, item D, a fee equivalent to 70
points.
Statutory Authority: MS s 115.03; 116.07
Disclaimer: These regulations may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.