Minnesota Administrative Rules
Agency 167 - Pollution Control Agency
Chapter 7002 - PERMIT FEES
WATER QUALITY PERMIT FEES
Part 7002.0250 - WATER QUALITY PERMIT APPLICATION FEE
Current through Register Vol. 49, No. 13, September 23, 2024
Subpart 1. Fee required.
A person who applies for a water quality permit to construct, install, modify, or operate a facility, as described in parts 7001.0020, subpart 2, items C to F, and 7090.0030, excluding changes in ownership or control, name or address changes other than changes in facility location, and interim and construction short-form permits issued under chapter 7020, shall submit with the application the appropriate application fee. Failure to submit the fee as specified in part 7002.0253, subpart 1, renders the application incomplete and the agency shall suspend processing of the application until the fee is received. Application fees are nonrefundable.
Subp. 2. Fee determination.
Application fees, except storm water application fees as required in part 7002.0254, are based on a point system established in part 7002.0253. The points shall be multiplied by the dollar per point value as determined in part 7002.0252.
Statutory Authority: MS s 115.03; 116.07