Current through Register Vol. 48, No. 39, March 25, 2024
Subpart 1.
Form.
The application for a hazardous waste facility permit
consists of Part A and Part B. The information requirements of Part A are set
forth in part
7001.0550. The information
requirements of Part B are set forth in parts
7001.0560 to
7001.0640. A person who submits
Part B of the application shall submit the information required by part
7001.0560 and shall also submit
any information required by parts
7001.0570 to
7001.0640 that is applicable to
the facility which is the subject of the application.
Subp. 2.
Timing of application.
Deadlines for the submission of a permit application for
existing and new hazardous waste facilities and for reissuance of existing
permits are as follows:
A. The owner
or operator of an existing hazardous waste facility shall submit Part A of the
application to the commissioner on or before the 90th day after April 23, 1984.
An owner or operator who has already submitted Part A of the application to the
Environmental Protection Agency need not submit Part A of the application to
the commissioner if the information submitted to the Environmental Protection
Agency is complete with respect to all portions of the facility and all wastes
stored, treated, or disposed of at the facility that are subject to regulation
under chapter 7045. If the information submitted to the Environmental
Protection Agency is not complete, the owner or operator shall submit an
amended Part A of the application to the commissioner on or before the 90th day
after April 23, 1984. The owner or operator may submit Part B of the
application at any time except that upon the request of the commissioner the
owner or operator shall submit Part B of the application not later than six
months after the date of receipt of the commissioner's request. A later date
for submission of Part B for a thermal treatment facility may be made under
part
7001.0700, subpart 11.
B. If a person proposes to construct a new
hazardous waste facility, the person shall submit Part A and Part B of the
application at least 180 days before the planned date of the commencement of
facility construction.
C. Part
7001.0040, subpart
3, governs the application
for the reissuance of existing permits except as provided in this part. When
the commissioner receives a written request that shows good cause for an
extension of time to file the application for permit reissuance, the
commissioner shall grant the extension if the final date for filing the
application does not extend beyond the expiration date of the permit. The
application must contain Part B of the application, completed to show all
information that is new or different from that contained in previously
submitted applications.
Subp.
3.
Updating permit applications.
An owner or operator of an existing hazardous waste facility
who has submitted Part A of the application but has not yet submitted Part B of
the application shall submit to the commissioner an amended Part A of the
application under the following circumstances:
A. if the submission of an amended
application is necessary to comply with part
7001.0650, subpart 5; or
B. if parts
7045.0102 to
7045.0141 are amended to list or
designate as hazardous a waste being treated, disposed of, or stored by the
owner or operator which was not listed or designated as hazardous at the time
the original Part A was submitted.
The owner or operator shall file the amended Part A not later
than July 23, 1984. An owner or operator who fails to submit an amended Part A
when required to do so shall not receive interim status for any wastes not
covered by a submitted Part A application.
Statutory Authority: MS s
116.07