The department shall make the following alternatives available for payment of permit applications:
A. a lump-sum payment at the time the permit application is submitted to the department;
B. quarterly payments based on the actual cost of labor and materials incurred that quarter to construct or install the power piping, anhydrous ammonia, or ammonia refrigeration systems; and
C. an annual payment based on the actual cost of labor and materials incurred to construct or install the power piping, anhydrous ammonia, or ammonia refrigeration systems. This payment method is only available under those circumstances where a licensed high pressure piping business does continuous high pressure piping work at a single work site. A log of work completed, with the cost of labor and materials, shall be maintained and provided to the department at inspection and with final payment. A nonrefundable $300 payment shall be made, in addition to the application filing fee, to the department when requesting this permit payment alternative.
The department shall not accept any applications for permits from any parties that are in arrears on their permit payments. The department shall revoke any approved permit where payments are 60 days in arrears.
Statutory Authority: MS s 16A.128; 16A.1285; 175.171; 183.44; 183.545; 326.46 to 326.521; 326B.90 to 326B.925; 326B.986