Subpart 1. General construction.
A temporarily sealed exploratory boring from which groundwater flows above the established ground surface without pumping and which does not require special construction under subpart 2 must be constructed to prevent erosion of the aquifer and confining layer. Casing must be installed into the flowing aquifer to prevent water flowing up the outside of the casing by either:
Subp. 2. Special construction required.
A temporarily sealed exploratory boring must be constructed according to subpart 3 when:
Subp. 3. Special construction standards.
A temporarily sealed exploratory boring requiring special construction under subpart 2 must be constructed by:
Subp. 4. Flow control.
A temporarily sealed flowing exploratory boring must be provided with flow control capable of stopping all flow.
Statutory Authority: MS s 103I.101